Operations News

  • SL6 Headnode work - stress testing ongoing without incident. (using realistic jobs from Alastair / Andrew if possible)
  • ATLAS have filled their available space in atlasStripInput, so we have paused draining pending deletions.
  • Draining - latest estimate is to complete draining in 7 weeks, assuming no breaks.
  • Webdav access for LHCb now working

Operations Problems

  • gdss720 / gdss763 are both drained, out of production and currently being worked on by Fabric team
  • gdss659 is still but will be decommissioned out of CASTOR.
  • lcgclsf02 had another sshd failure on Wednesday. We believe this is due to the xroot service on this node spawning an excessive number of subprocesses, which ran into a hard limit in the OS. This will be resolved by shifting this node's xroot responsibilities over to a dedicated node.
  • Last week's SRM SAM test failures on LHCB/CMS and callout on pluto have been explained, and are due to the details of our DB setup. The issue will be fixed when we upgrade to 2.1.14-14.

Blocking Issues

  • grid ftp bug in SL6 - stops any globus copy if a client is using a particular library. This is a show stopper for SL6 on disk server.


Planned, Scheduled and Cancelled Interventions

  • A Tier 1 Database cleanup is planned so as to eliminate a number of excess tables and other entities left over from previous CASTOR versions. This will be change-controlled in the near future.
  • Upgrade of CASTOR to SL6 (December)
  • Upgrade Oracle DB to version 11.2.0.4 (Late February?)
  • Upgrade CASTOR to version 2.1.14-14 OR 2.1.14-15 (Early February)


Advanced Planning

Tasks

  • Plan and publish SL6 deployment plans
  • Plan to ensure PreProd represents production in terms of hardware generation are underway
  • Possible future upgrade to CASTOR 2.1.14-15 post-Christmas
  • Switch from admin machines: lcgccvm02 to lcgcadm05
  • Correct partitioning alignment issue (3rd CASTOR partition) on new castor disk servers

Interventions

  • Upgrade Production headnodes to SL6 - first upgrade Tuesday 2nd December. Next upgrades (ATLAS and CMS) planned for 9th and 10th December.

Actions

Staffing

  • Castor on Call person
    • Rob


  • Staff absence/out of the office:
    • Rob - Out at least 1 day
    • Brian - Out Tuesday-Friday.