Overview of Milestones and Metrics
Key Metrics
Owner | Description | Target | Achieved |
---|---|---|---|
Gareth Smith | Overall Tier-1 SAM Availability (last week) | 97% | 100% |
Gareth Smith | Alice SAM Availability (Sep) | 97% | 81% |
Gareth Smith | ATLAS SAM Availability (Sep) | 97% | 85% |
Gareth Smith | CMS SAM availability (Sep) | 97% | 87% |
Gareth Smith | LHCB SAM availability (Sep) | 97% | 91% |
Andrew Sansum | Fraction of (GRIDPP funded) Tier-1 Staff in Post (Sep) | 93% | 103% |
Gareth Smith | Number of days where called out (last spreadsheet full week) | 3 | 0 |
Matt Hodges | Percentage met of UB allocation of disk (Sep) | 100% | To follow - UB schedule not finalised yet |
Matt Hodges | Job Efficiency (Sep) | 85% | 72% |
Matt Hodges | Farm Occupancy (Sep) | 85% | To follow - UB schedule not finalised yet |
Matt Viljoen | Number of >Severe CASTOR Incidents (Sept) | 6 | 2 |
Key Production Milestones
See myactions:
https://myactions.gridpp.rl.ac.uk/all/where/category_name/Operational/
High Level Schedule
LHC commissioning appears to be on track and beam injection tests have commenced.
Event | Scehdule |
---|---|
Tier-1 Stability Period (2) | October-mid-November |
LHC First beam | mid November |
LHC Standby | December 19th |
Restart | 4th January |
Run ends | October 2010 |
Disaster Management
- Multiple RAID Array failures (was 4). Now level 2. So far have failed to find electrical problem causing the EMC RAID arrays to be unstable.
- Disk deployment (level 2) ongoing testing with Viglen. Still problems with hardware, and recently tested solutions have failed acceptance. Expect to escalate this at this weeks review meeting.
Purchasing and Finance
- GRIDPP finalised high level spend plan.
- Disk tender at ITT evaluation stage.
- CPU PQQ at evaluation stage.
- Tape drives arrived.
- Finalising spend plan.
Staffing
At full complement
PMB Experiment Reports
ATLAS
CMS
LHCB
Hardware Deployment Report (Chris)
Team Reports
Fabric
RAL Tier1 weekly operations Fabric 20091109
Grid Services
http://www.gridpp.ac.uk/wiki/RAL_Tier1_weekly_operations_Grid_20091109
CASTOR
http://www.gridpp.ac.uk/wiki/RAL_Tier1_weekly_operations_castor_09/11/2009
Database
http://www.gridpp.ac.uk/wiki/Operations_Report_09/11/2009