RAL Tier1 weekly operations Grid 20110620
From GridPP Wiki
Contents
Operational Issues
Description | Start | End | Affected VO(s) | Severity | Status |
---|
Downtimes
Description | Hosts | Type | Start | End | Affected VO(s) |
---|---|---|---|---|---|
Blocking Issues
Description | Requested Date | Required By Date | Priority | Status |
---|---|---|---|---|
Developments/Plans
Highlights for Tier-1 Ops Meeting
Highlights for Tier-1 VO Liaison Meeting
Detailed Individual Reports
Alastair
- Working on permission change. [Ongoing]
- Looking at Hammer Cloud test results across UK Cloud.
- Frontier, testing new API, monitoring packagaes and helping deploy new box.
Andrew
- CMS xrootd testing [Ongoing]
- Setup gridTest queue [Done]
- Maui config change (each LHC VO now has their own QoS) [Done]
- Tested multiple default ACLs; writing change control for CMS ACL change [Ongoing]
- At CERN this week
Catalin
- lcgce05 quattorisation (non-LHC) [done]
- worked on pheno issue on WMS03 (huge output files) [done]
- involved with CREAM CEs installation and configuration [ongoing]
- work on quattorised ATLAS Frontier installation and update documentation [ongoing]
- hand over ATLAS Frontier VOBOX installation to Alastair for tests [ongoing]
- prepare GST view on Quattor status [ongoing]
- work on BDII stability [stalled]
- update glite LFC [stalled]
Derek
(SCT - Mon-Thu, Tier 1 - Fri (or as requested))
- Quattor tidy up [ongoing]
- Metrics - handed over to Garetg [done]
VO Reports
ALICE
ATLAS
CMS
- Ongoing CASTOR issue: sometimes there are periods where incoming/outgoing transfers fail due to PrepareToPuts and PrepareToGets taking longer than 180s. Similarly for SAM tests.
LHCb
OnCall/AoD Cover
- Primary OnCall: Catalin (Mon-Sun)
- Grid OnCall:
- AoD: