RAL Tier1 weekly Operations Grid 20130218

From GridPP Wiki
Jump to: navigation, search

Operational Issues

Description Start End Affected VO(s) Severity Status

Downtimes

Description Hosts Type Start End Affected VO(s)

Blocking Issues

Description Requested Date Required By Date Priority Status
Site firewall hole adjustment for lcggwms02 (rt #107281) 2013-01-30 2013-02-06 Medium Request not submitted to networking yet

Developments/Plans

Highlights for Tier-1 Ops Meeting

Highlights for Tier-1 VO Liaison Meeting

Detailed Individual Reports

Andrew

  • Last week:
    • New batch system testing
    • GridPP Cloud testing
    • CMS processing
  • Coming week:
    • WLCG accounting
    • Deploy FTS 2.2.9 SL5 & SL6 for verification/staged-rollout
    • Preparations for capacity signoff meeting
    • CMS processing

Catalin

  • Last week
  • This week

Ian

  • Last week:
  • Coming week:

James

  • Last Week
  • This Week

Orlin

  • Last Week
    • Install & Test EMI2/SL6 WNs on the gridSL6 queue [testing ongoing]
    • Clean up & optimize quattor configuration for EMI2/SL6 WNs [ongoing]
    • Move the gridWN and gridTest queues to EMI2/SL6 CREAMCE lcgce07 [ongoing]
    • Bring the Testbed back in order, check the list of services [ongoing]
    • Install & Test Latest EMI2 update for SL5 WNs production WNs [testing ongoing]
    • Learn more about Cloud computing - Open Nebula; EC2; OpenStack & do some tests [ongoing]
    • Update the annual Job plan [done]
  • This Week
    • Move the gridWN and gridTest queues to EMI2/SL6 CREAMCE lcgce07 [ongoing]
    • Install & Test EMI2/SL6 WNs on the gridSL6 queue [testing ongoing]
    • Clean up & optimize quattor configuration for EMI2/SL6 WNs [ongoing]
    • Bring the Testbed back in order, check the list of services [ongoing]
    • Install & Test Latest EMI2 update for SL5 production WNs [testing ongoing]
    • Learn more about Cloud computing - Open Nebula; EC2; OpenStack & do some tests [ongoing]
    • Prepare & Install Open Nebula on a physical host suitable for virtualization [to do]
    • Install some EMI2/SL6 Worker Nodes to tests cleaned up templates before deploying the cluster [to do]

VO Reports

ALICE

ATLAS

CMS

LHCb

OnCall/AoD Cover

OnCall Rota

  • Grid OnCall: Andrew (Mon- Sun)

Absences

Andrew - Tues A/L

Ian - Mon & Tues ? A/L