Production Team Report 2009-09-07

From GridPP Wiki
Jump to: navigation, search

RAL Tier1 Production Team Report for 9th September 2009.

AoD This Week

Mon/Tue: John Wed: James Thorne Wed-Fri: Tiju

Last Week

(Short Week - only Wed - Fri)

  • Gareth: Some AoD, Post Mortem on A/C issues;
  • John: AoD support and investigations.
  • Tiju: Dashboard development and announcement.

This Week

  • Gareth, Tiju: Attending GridPP.

Changes to Operating procedures

  • Friday review of systems that will come out of Nagios downtimes over the weekend.

Declared Outages in GOC DB

  • 7-Sep: WMS01 upgrade.
  • 8-Sep: OGMA (Atlas 3d) database upgarde to 63 bit.
  • 9-Sep: GEN instance SRM upgrade (2.8-0)
  • 14-Sep: LHCb instance SRM upgrade (2.8-0)
  • 14-Sep: (and onwards) CEs for batch SL5 migration.
  • 16-Sep: CMS instance SRM upgrade (2.8-0)
  • 21-Sep: Atlas instance SRM upgrade (2.8-0)

Other Outages Awaiting Finalization

  • 15-Sep: Castor nameserver upgrade and kernel updates on database systems.
  • 22-Sep: Outage for UPS test. (Castor quiescent).


Other Operation Notes

  • Note a number of staff away for GridPP meeting.