Operations Report 23/12/2012

From GridPP Wiki
Jump to: navigation, search

Summary of Previous Week

  • 3D: Ogma (3D ATLAS conditions) upgraded to 11g
  • CASTOR: ATLAS SRM now running on new production hardware
  • CASTOR: DLF partitioning now fixed

Operational Issues and Incidents

  • CASTOR:

Plans for Week(s) Ahead

  • CASTOR: Testing production schema dumps with 2.1.11 upgrade scripts
  • 3D: Preparation for LHCb 11g upgrade


Downtimes and At Risk

Description Start End Affected VO(s) Type

Development Priorities

  • Test and migrate to new HW
  • Migrate to 11G
  • GC resilience

Requirements and Blocking Issues

  • None


OnCall

  • Rich

Absences

Adrian: Mon
Eddy: Mon-Wed

Summary of Previous Week

  • 3D: Ogma (3D ATLAS conditions) upgraded to 11g
  • CASTOR: ATLAS SRM now running on new production hardware
  • CASTOR: DLF partitioning now fixed

Operational Issues and Incidents

  • CASTOR:

Plans for Week(s) Ahead

  • CASTOR: Testing production schema dumps with 2.1.11 upgrade scripts
  • 3D: Preparation for LHCb 11g upgrade


Downtimes and At Risk

Description Start End Affected VO(s) Type

Development Priorities

  • Test and migrate to new HW
  • Migrate to 11G
  • GC resilience

Requirements and Blocking Issues

  • None


OnCall

  • Rich

Absences

Adrian: Mon
Eddy: Mon-Wed