| When? | What?
|
| February 10th | Stage in Tests from Tape to disk cache.
|
| March | RAL to be used as repository of EVNT data
|
| Starting sometime the week of March 9th ( Delayed) | Large-scale reprocessing exercise. This is likely to produce ~20-25TB of files to be stored at RAL. The majority of this will be done in ~ a week but with a tail of probably at least a week.
|
| Likely 1st April ( This is not a joke) | High rate T1-T1 test to be repeated after success of January's test.
|
| ??? | Test of FTS channel TCP settings. To be tested firstly on BNL-RAL channel to see effect on large RTT WAN traffic.
|
| ??? | Possibly test with "Hammer Cloud" system
|
| ??? | Experiment require Stable Site
|
| ??? | Cosmics Data taking
|
| September 09? | Collision Data Taking
|