Production Team Report 2010-05-10
From GridPP Wiki
Contents
RAL Tier1 Production Team Report for 26th April 2010.
AoD This Week
Mon & Tues: John Wed: Gareth Thu & Fri: John
Last Week (19 April - 26 April)
- Gareth: AoD (<1 day), APRs, EMCvUPS discussion, HEP SYSMAN planning.
- John: APR, some scripting and dumped wiki
- Tiju: AoD (2 days), APR
Changes to Operating procedures
- Use of fortnightly Tier1 co-ordination meeting to schedule Tier1s during technical stops. (CERN will try and keep with the dates of the technical stops.)
Declared Outages in GOC DB
- Decommissioning NGS CE: 6 to 14 May.
- Reconfiguring lcgce06 to enable mappings for glexec 10 -12 May
- At Risk for UPS test - 1st June.
Advanced Warning
- CEs will be configured for glexec in rotation.
- Clean-up of Sub-request table within Castor Oracle databases. At Risk on Castor instances in rotation.