Summary of Previous Week

Developments

  • installing c2probe (Cheney, Tim, Rich)
  • SRM development (Shaun)
  • finishing off LSF reconfiguration tests (Chris)
  • 2.1.7-27 certification (Chris)
  • adding virtual disk servers to preproduction (Matt)

1.2 Developments- prioritized

  • R89 move and testing CASTOR afterwards (All)
  • 2.1.7-27 Certification (Chris)
  • SRM development (Shaun)
  • CIP development (Jens)

Ongoing

  • Setting up Preproduction (Matt)
  • Decommissioning gdss314/315 (Matt)
  • Test 2.1.8-8 on tape drives (Tim)
  • Prepare certification platform for stress testing (crosstalk investigations suspended) (Chris/Matt)
  • adding virtual disk servers to preproduction (Matt)

Operations Issues

none

Blocking issues

none

Scheduled and Cancelled Down Times

Entries in/planned to go to GOCDB

Description Start End Type Affected VO(s)
R89 move 25/6/09 0600 6/6/09 1200 Downtime All
R89 move 6/6/09 1200 10/6/09 1700 At Risk All
Apply Oracle BigID patch 13/7/09 0800 13/7/09 1700 At Risk All
2.1.7-27 upgrade and LSF reconfiguration 14/7/09 0800 14/7/09 1700 Downtime All
2.1.7-27 upgrade and LSF reconfiguration 14/7/09 0700 15/7/09 1700 At Risk All

Advanced Planning

  • SRM 2.8 upgrade
  • Start using Black and White lists
  • CIP upgrade to include nearline publishing


Staffing

  • Castor on Call person (is also Castor on Day Duty): Chris