RAL Tier1 weekly operations castor 17/09/2012
From GridPP Wiki
Revision as of 14:45, 17 September 2012 by Matt viljoen (Talk | contribs)
Contents
Operations News
- Late testing against preprod showed problems against 2.1.12 - forcing LHCb upgrade to be postponed:
- xroot component kept crashing during testing on preprod due to a corrupted installation. Once xroot RPMs were reinstalled, everything was ok.
- CIP broken due to architectural changes (breaking of svcclass/tapepool link in DB). A new version has been developed which relies upon the links being hardcoded in a configuration file.
- Transfer manager has been doubled up across all instances
Operations Problems
- none
Blocking Issues
none
Planned, Scheduled and Cancelled Interventions
Entries in/planned to go to GOCDB
Description | Start | End | Type | Affected VO(s) | Lead by |
---|---|---|---|---|---|
2.1.12-10 Stager upgrade | 25/09/12 08:00 | 25/09/12 14:00 | Downtime | ATLAS | Matthew |
Advanced Planning
Tasks
- Test and certify 2.1.12-10
- Test and certify 2.1.13-??
Interventions
- Stager upgrades to 2.1.12 on Tier1 instances now we're happy with TM/TG (12Q4)
Staffing
- Castor on Call person
- Matthew
- Staff absence/out of the office:
- Jens working out of the office all week