RAL Tier1 weekly operations Overview 20090921
From GridPP Wiki
Revision as of 10:24, 21 September 2009 by Andrew sansum (Talk | contribs)
Contents
Overview of Milestones and Metrics
Key High Level dates
- Repairs continue - very challenging program of work
- Injection tests, late October.
- LHC ready for beam by mid-November.
- Commissioning needs 28 days beam time (factor 2 elapsed)
- Standby December 19th
- Restart recommissioning commences January 4th
- Beam 11th January
- Scheduled 3 day downtime (Monday-Wed every 4 weeks) restart on the Thursday.
- Run until September then 2 weeks down while prepare for heavy ions
- Run ends in October
- Tier-1 software freeze date end of September
Key Metrics
Owner | Description | Target | Achieved |
---|---|---|---|
Gareth Smith | Overall Tier-1 SAM Availability (last week) | 97% | 71% |
Gareth Smith | Alice SAM Availability (Aug) | 97% | 77% |
Gareth Smith | ATLAS SAM Availability (Aug) | 97% | 75% |
Gareth Smith | CMS SAM availability (Aug) | 97% | 77% |
Gareth Smith | LHCB SAM availability (Aug) | 97% | 78% |
Andrew Sansum | Fraction of Tier-1 Staff in Post (Aug) | 93% | 103% |
Gareth Smith | Number of days where called out (last spreadsheet full week) | 3 | 2 |
Matt Hodges | Percentage met of UB allocation of disk (Aug) | 100% | |
Matt Hodges | Job Efficiency (Aug) | 85% | 67% |
Matt Hodges | Farm Occupancy (Aug) | 85% | 41% |
Matt Viljoen | Number of >Severe CASTOR Incidents (Aug) | 6 |
Key Production Milestones
See myactions:
https://myactions.gridpp.rl.ac.uk/all/where/category_name/Operational/
High Level Schedule
Final Update Window Mon 13/07/09 30/09/09 Tier-1 Stability Period (2) October-mid-November LHC First beam mid November
Disaster Management
- Swine Flu (H1N1) downgraded to level 1. No regular meetings, will re-activate when case frequency increases
- Disk deployment (level 2) ongoing testing with Viglen. Increasing likelihood that we will escalate to L3 if no progress soon.
- Machine room air-conditioning. Now level 2.
- Water leak
Swine Flu Response Plan
See: https://wiki.e-science.cclrc.ac.uk/web1/bin/view/EScienceInternal/TierOneSwineFlu
Purchasing and Finance
- GRIDPP finalising high level spend plan.
- Disk tender at ITT evaluation stage.
- CPU PQQ at evaluation stage.
- Tape drive purchases being planned.
- Beginning to build spend plan.
Staffing
- Second experiment support post, start date 5th October.
PMB Experiment Reports
ATLAS
CMS
LHCB
Hardware Deployment Report
Team Reports
Fabric
RAL Tier1 weekly operations Fabric 20090921
Grid Services
http://www.gridpp.ac.uk/wiki/RAL_Tier1_weekly_operations_Grid_20090921
CASTOR
http://www.gridpp.ac.uk/wiki/RAL_Tier1_weekly_operations_castor_21/09/2009
Database
http://www.gridpp.ac.uk/wiki/Operations_Report_21/09/2009