| 20140312-01 || Normal || ALICE || Lee || Check ALICE plans for tape access || Done|| 2013-04-30
 
 
|-
 
|-
 
| 20131023-03 || Normal || ATLAS || Matthew || Report back about ATLAS CASTOR deletion problem after F2F discussion with developers || Closed. || 2014-01-08
 
| 20131023-03 || Normal || ATLAS || Matthew || Report back about ATLAS CASTOR deletion problem after F2F discussion with developers || Closed. || 2014-01-08
|-
 
|20131023-01  || Normal || N/A || Catalin || Send Henry details about UI baseline version for SHA-2 compliance || Done. || 2013-10-30
 
|-
 
| 20130109-01 || Medium || ALICE || Andrew L, Shaun || Check ALICE tape usage & allocation. || Done || 2013-01-16
 
|-
 
| 20130116-01 || Medium || T2K || Alastair, Shaun || Talk to Jonathan about T2K storage. || Done || 2013-01-23
 
|-
 
| 20130116-01 || Medium || T2K || Alastair || Write document: Idiot's guide to storage at RAL for non-LHC VOs. || Done. || 2013-01-30
 
|-
 
| 20130123-01 || Medium ||  || Andrew S || Try to ensure that Friday's electrical work is delayed || Closed || 2013-01-30
 
|-
 
| 20130206-01 || Medium || ALICE || Rob || Check consistency & accuracy of ALICE disk reporting || Closed || 2013-02-20
 
|-
 
| 20130306-01 || Medium || MICE || Henry || Henry to email production team about MICE computing contacts. || Done. || 2013-03-13
 
|-
 
| 20130313-02 || Medium ||  || Andrew L || Setup a place for previous special presentations. || Done. || 2013-04-03
 
|-
 
| 20130220-01 || Medium || T2K || Gareth || Post-mortem on gdss594 || Done. || 2013-04-10
 
|-
 
| 20130313-01 || Medium || ATLAS || Alastair || Make sure ATLAS GGUS ticket about CASTOR problems affecting FTS is up-to-date || Closed || 2013-05-01
 
|-
 
| 20130123-01 || Medium ||    || Gareth || Ensure that the problem of CRL expiry is addressed || Closed || 2013-09-18
 
 
|-
 
|-
 
| 20140108-01 || Normal || ALICE || Gareth || Why was the ALICE VOBOX rebooted 19 days ago? What happened to it? || Closed || 2014-02-05
 
| 20140108-01 || Normal || ALICE || Gareth || Why was the ALICE VOBOX rebooted 19 days ago? What happened to it? || Closed || 2014-02-05

Revision as of 09:29, 20 May 2015


Covers all aspects of the Tier1. Meeting access information is available from Indico. Previous special presentations can be found here.

Agenda

Chairman: Andrew Sansum

Secretary: Andrew Lahiff

  1. Summary of Operational Status and Issues
  2. Highlights/summary of the Tier1 Monday operations meeting.
    • Grid Services
    • Fabric
    • CASTOR
    • Other
  3. Experiment plans and operational issues
    • CMS
    • ATLAS
    • LHCb
    • ALICE
    • Others
  4. Special topics/presentations (agreed in advance)
    • None
  5. Actions
  6. Highlights for Operations Bulletin Latest
  7. AoB

Open Actions

Action ID Priority Experiment(s) Owner Action Status

Completed Actions

Archives of actions completed can be found at:


Action ID Priority Experiment(s) Owner Action Status Completed date
20131023-03 Normal ATLAS Matthew Report back about ATLAS CASTOR deletion problem after F2F discussion with developers Closed. 2014-01-08
20140108-01 Normal ALICE Gareth Why was the ALICE VOBOX rebooted 19 days ago? What happened to it? Closed 2014-02-05
20131023-02 Normal LHCb Jens Explain why SRM and CIP/BDII usage for LHCb are different and inform Raja which to use. Closed 2014-02-12
20140219-01 Normal N/A John Start post-mortem of loss of FTS3 database VM Closed 2014-02-25
20140225-02 Normal MICE Catalin Give MICE access to all WMSs at RAL Closed 2014-03-18
20140402-01 Normal N/A Gareth Perfsonar router changes need to be completed Done. 2014-04-09
20140225-01 Normal MICE Catalin Investigate why it takes 5 hours for MICE to unpack a tarball Closed 2014-04-16
20140205-01 Normal Non-LHC Catalin Ensure that non-LHC VOs are aware of alternatives to the NFS software server Closed 2014-04-23
20140423-02 Normal All Martin Liaise with networking about OPN failure over issues Closed 2014-05-07
20140709-01 Normal N/A Gareth Provide a short summary about the recent and upcoming network changes. Closed 2014-07-23
20140423-01 Normal non-LHC Gareth Finalize plans for termination of the software server Closed 2014-08-06
20140827-01 Normal N/A Martin Report back from MROG meeting (was "Follow up with testing of electrical circuits in LPD & HPD rooms") Done 2014-09-17
20140827-02 Normal N/A Rob Report on plans for Castor 2.1.15 upgrade. Done 2014-10-28
20141001-01 Normal N/A Andrew L Provide Wiki page (for VOs) detailing effect of cgroups. Done 2014-10-28
20150128-01 Normal N/A Andrew L Remove links to Fabric and Grid Services Done 2015-02-04
20150128-02 Normal CMS Andrew L Ensure the relevant people are looking into CMS CASTOR problems Closed 2015-02-11
20141008-01 Normal N/A Tim F Discuss data retention after experiment shutdown with H1 (Response: Data can be deleted) Closed 2015-03-18
20150313-01 Normal N/A Andrew S Discuss with PMB decommissioning of CREAM CEs Closed 2015-05-06