RAL Tier1 CASTOR planning ALICE

From GridPP Wiki
Revision as of 14:37, 11 February 2009 by Cristina lazzeroni 2 (Talk | contribs)

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search
When? What?
2009 MC production of 2009-ALICE-setup p+p.
January 2009 Implementation of new WMS sensor - this is provisional and will not be put in production before January 2009.
Feb 2009 MC pre-productions of 2009-ALICE-setup p+p and validation.
~20 Feb 2009 Start production of 100 Mio pp events.