Action ID Priority Experiment(s) Owner Action Status Completed date
20131023-03 Normal ATLAS Matthew Report back about ATLAS CASTOR deletion problem after F2F discussion with developers Closed. 2014-01-08
20140108-01 Normal ALICE Gareth Why was the ALICE VOBOX rebooted 19 days ago? What happened to it? Closed 2014-02-05
20131023-02 Normal LHCb Jens Explain why SRM and CIP/BDII usage for LHCb are different and inform Raja which to use. Closed 2014-02-12
20140219-01 Normal N/A John Start post-mortem of loss of FTS3 database VM Closed 2014-02-25
20140225-02 Normal MICE Catalin Give MICE access to all WMSs at RAL Closed 2014-03-18
20140402-01 Normal N/A Gareth Perfsonar router changes need to be completed Done. 2014-04-09
20140225-01 Normal MICE Catalin Investigate why it takes 5 hours for MICE to unpack a tarball Closed 2014-04-16
20140205-01 Normal Non-LHC Catalin Ensure that non-LHC VOs are aware of alternatives to the NFS software server Closed 2014-04-23
20140423-02 Normal All Martin Liaise with networking about OPN failure over issues Closed 2014-05-07
20140709-01 Normal N/A Gareth Provide a short summary about the recent and upcoming network changes. Closed 2014-07-23
20140423-01 Normal non-LHC Gareth Finalize plans for termination of the software server Closed 2014-08-06
20140827-01 Normal N/A Martin Report back from MROG meeting (was "Follow up with testing of electrical circuits in LPD & HPD rooms") Done 2014-09-17
20140827-02 Normal N/A Rob Report on plans for Castor 2.1.15 upgrade. Done 2014-10-28
20141001-01 Normal N/A Andrew L Provide Wiki page (for VOs) detailing effect of cgroups. Done 2014-10-28