Summary of Previous Week
- CASTOR: Stager Sync enabled on few ATLAS disk servers at time to find out which one was causing the excessive redo log generation.
- ALL: Learning about PostgreSQL
- LFC/FTS/LFC: Change control submitted for next stage of migration
Operational Issues and Incidents
- None
Plans for Week(s) Ahead
- CASTOR: Retire old pre-prod hardware
- CASTOR: Working on solving the Neptune logging issues
Downtimes and At Risk
Description | Start | End | Affected VO(s) | Type |
---|
Development Priorities
- Test and migrate to new HW
- Implement GC resilience
Requirements and Blocking Issues
- None
OnCall
- Carmine
Absences
- Eddy - Whole week (On Holiday)