RAL Tier1 weekly operations Grid 20111107
From GridPP Wiki
Revision as of 11:02, 7 November 2011 by Catalin condurache (Talk | contribs)
Contents
Operational Issues
Description | Start | End | Affected VO(s) | Severity | Status |
---|---|---|---|---|---|
Downtimes
Description | Hosts | Type | Start | End | Affected VO(s) |
---|---|---|---|---|---|
Blocking Issues
Description | Requested Date | Required By Date | Priority | Status |
---|---|---|---|---|
Developments/Plans
Highlights for Tier-1 Ops Meeting
Highlights for Tier-1 VO Liaison Meeting
Detailed Individual Reports
Alastair
Andrew
- October accounting [Done]
- Updated to capacity planning system, various meetings [Done]
- Added 2 new FTS channels for ATLAS UCL-HEP [Done]
- Trying to get access to WMAgent webpages [Ongoing]
- Dealing with setting up new VO SNO+ [Ongoing]
- EMI/UMD [Ongoing]
Catalin
- LHC CREAM-CE access re-configuration [done]
- lcgce06 drain + decommission [done]
- work on EMI/UMD BDII deployments [ongoing]
- deploy first UMD site-BDII [ongoing]
- HEPSYSMAN QMUL (Thu 10 Nov)
VO Reports
ALICE
ATLAS
CMS
LHCb
OnCall/AoD Cover
- Primary OnCall: Catalin (Mon-Sun)
- Grid OnCall: