Difference between revisions of "RAL Tier1 weekly operations Grid 20120806"

From GridPP Wiki
Jump to: navigation, search
 
(No difference)

Latest revision as of 15:00, 6 August 2012

Operational Issues

Description Start End Affected VO(s) Severity Status

Downtimes

Description Hosts Type Start End Affected VO(s)

Blocking Issues

Description Requested Date Required By Date Priority Status

Developments/Plans

Highlights for Tier-1 Ops Meeting

Highlights for Tier-1 VO Liaison Meeting

Detailed Individual Reports

Andrew

  • Last week:
    • Some kernel/errata upgrades
    • Completed moving FTS agents to VMs
    • Started July accounting
    • Prepared a presentation about possible batch systems, requirements; work on installing/configuring Condor, Grid Engine, Torque 4
    • CMS processing
  • Coming week:
    • Functional tests of FTS 3
    • Batch system testing
    • Complete July accounting
    • CMS processing

Catalin

Ian

  • Last week:


  • Coming week:


James

Orlin

  • Implement centralized banning policy Argus PAP server/client and test it on WNs. [done]
  • Prepare & Change the gLexec WN authentication from SCAS to ARGUS on all production WNs. [done]
  • Prepare NFS Server for production - write change-control, perform tests & implement failover/backup. [ongoing]
  • Check how EMI-2 SL-6 WNs can be implemented at RAL. [ongoing]
  • Create & Test Quattor templates for EMI-2 SL-6 WNs. [ongoing]

VO Reports

ALICE

ATLAS

CMS

LHCb

OnCall/AoD Cover

OnCall Rota

  • Primary OnCall: Catalin (Mon-Sun)