RAL Tier1 Production Team Report for 8th November 2010.
AoD This Week
Mon - Tue: John Wed: Catalin Thu - Fri: John
Last week
- Gareth: AoD(1day), Discussions on wrapping up EMC UPS power issues & monitoring tape issues. Drafted Post Mortem on LHCb issues, Web pages for HEP SYSMAN meeting.
- John: Looking at Nagios test for read only file systems.
- Tiju: AoD(4days) Investigate Icinga and other Nagios possibilities.
Changes to Operating procedures
- None
Declared Outages in GOC DB
- Wednesday 10th Nov. 08:00-16:00 Outage on srm-lhcb. Upgrading disk servers to 64-bit OS.
- Tue - Thu 16-18 Nov. CMS Castor 2.1.9 upgrade.
Advanced Warning
- Tuesday 9th Nov. Mon -> APEL switch over.
- Remaining Castor: Current scheduling (T.B.C) on following dates:
- Upgrade ATLAS - Monday - Wednesday 6 - 8 December.
- Weekend 11/12 Dec: Power outage in Atlas building.
- Monday 13th December - UPS test.
- Either Tuesday 23 or 30 Nov: Intervention on tape robot to fix power for cooling problem.
Other Changes
- Fabric:
- Tape Drive Microcode Update.
- Double the network link to the tape robot stack (stack 12), postponed from the last TS. (Requires Castor stop).
- Swap out the older of the pair of SAN switches in the Tier1 Oracle databases for its new replacement. (Requires FTS, LFC, 3D stop).
- Database:
- Re-visit non-Castor database multipathing
- Grid Services:
- None
- Castor:
- SRM updates for LHCb
- Networks:
- None