When? | What? |
---|---|
April 2009 | Letters of Intent from the detector concepts due |
December 2008-April2009 | Simulation and Reconstruction of data samples, Benchmarking analyses for the Letters of Intent |
March 2009 | Start of cleanup of data files, removal of duplicates. Hopefully finished before machine room migration. |
March 31st 2009 | Sucessful submission of the LoI to the international detectors advisory group (IDAG) |
after April 2009 | expected quiet time (barring schedule slippage and until further notice). CASTOR use not expected to increase |
May 2009 | IDAG requested further studies requiring additional samples. This 'addendum' should be turned in by June 15th. Production should be completed by end of May to allow for analysis and write-up. |