Production Team Report 2010-08-09

From GridPP Wiki
Revision as of 08:15, 10 August 2010 by Tiju idiculla (Talk | contribs)

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

RAL Tier1 Production Team Report for 9th August 2010.

AoD This Week

Mon: Tiju Tues: James T. Wed: Gareth Thu & Fri: John

Last week

  • Gareth: AoD (2 days), updated Post Mortem script, looked at EMCvUPS options, my metrics, e-Science Services Co-ordination review of JiscMail.
  • John: A/L (3 days)
  • Tiju: AoD (3 days), Modem script,understanding iSCSI

Changes to Operating procedures

  • Revised Post Mortem Template.

Declared Outages in GOC DB

None.

Advanced Warning

  • Day not specified: Test of seal under 1st floor kitchen.
  • Next week - WMS03 update.

Other Changes

  • Fabric:
    • Double the network link to the tape robot stack (stack 12), postponed from the last TS. (Requires Castor stop).
    • Swap out the older of the pair of SAN switches in the Tier1 Oracle databases for its new replacement. (Requires FTS, LFC, 3D stop).
    • New kernels and glibc updates on non-castor Oracle RAC nodes. (Done for LUGH).
    • Updates to amanda backup - unblocking possible other updates.
  • Database:
    • Re-visit non-Castor database mulitpathing
  • Grid Services:
    • Worker node update (to latest glite version).
  • Castor:
    • Possible SRM update
  • Networks:
    • Commissioning OPN link