restricted EU 2007


Project Start Date: Mon 16/04/07
Project Finish Date: Tue 11/03/08

Task_Data

ID
Task_Name
DurationStart_DateFinish_DatePredecessorsResource_Names
1
Prepare Request for Information Questionaire
1.4 wksTue 10/04/07Wed 18/04/07  
2
Prepare Supplier Evaluation Criteria
1.4 wksTue 10/04/07Wed 18/04/07  
3
GRIDPP confirm Approximate Scale of Purchase
0 daysWed 18/04/07Wed 18/04/072 
4
Procurement Submits OJEC Notice
1 wkThu 19/04/07Wed 25/04/071,3,2 
5
Tender Launched
0 daysWed 25/04/07Wed 25/04/074 
6
Suppliers respond to Invitation
30 daysThu 26/04/07Fri 25/05/075 
7
Tender Closed
0 daysFri 25/05/07Fri 25/05/076 
8
Supplier Evaluation
3 wksMon 28/05/07Fri 15/06/077 
9
Agree Hardware Specification
4 wksMon 16/04/07Fri 11/05/07  
10
Prepare Tender Document
3 wksMon 14/05/07Fri 01/06/079 
11
Prepare Evaluation Document
3 wksMon 14/05/07Fri 01/06/079 
12
Prefered Suppliers Selected
0 daysFri 15/06/07Fri 15/06/078 
13
Financial approval Agreed
0 daysFri 01/06/07Fri 01/06/0710FF 
14
Tender Documents Issued
1 wkMon 18/06/07Fri 22/06/0710,11,13,12 
15
Suppliers Respond to tender
35 daysSat 23/06/07Fri 27/07/0714 
16
Tender Evaluation
3 wksMon 30/07/07Fri 17/08/0715 
17
Prefered Supplier Selected
0 daysFri 17/08/07Fri 17/08/0716 
18
Suppliers Notified of outcome
0 daysFri 17/08/07Fri 17/08/0717 
19
Standstill
10 daysSat 18/08/07Mon 27/08/0718 
20
Procurement Prepare Order
1 wkMon 20/08/07Fri 24/08/0716 
21
Order Placed
0 daysMon 27/08/07Mon 27/08/0720,19 
22
Confirm Order Specification with Machine Room
0 daysMon 27/08/07Mon 27/08/0721 
23
Install Power Distribution
6 wksTue 28/08/07Mon 08/10/0722 
24
Supplier Builds Equipment
8 wksTue 28/08/07Mon 22/10/0721 
25
Equipment Delivered
0 daysMon 22/10/07Mon 22/10/0724,23 
26
Equipment Installed and Commisioned
2 wksTue 23/10/07Mon 05/11/0725 
27
RAL Acceptance Tests Phase I
4 wksTue 06/11/07Mon 03/12/0726 
28
CPU Installation Contingency
4 wksTue 04/12/07Mon 31/12/0727 
29
CPU Nodes Accepted
0 daysMon 31/12/07Mon 31/12/0728 
30
CPU Nodes Available to Users
2 wksTue 01/01/08Mon 14/01/0829 
31
Disk Installation Contingency
8 wksTue 04/12/07Mon 28/01/0827 
32
Disk Nodes Accepted
1 day?Tue 29/01/08Tue 29/01/0831 
33
20% Disk Nodes Available to Users
2 wksWed 30/01/08Tue 12/02/0832 
34
50% Disk Nodes Available to Users
2 wksWed 13/02/08Tue 26/02/0833 
35
100% Disk Nodes Available to Users
2 wksWed 27/02/08Tue 11/03/0834 