MSProj11


Project Start Date: Fri 01/06/07
Project Finish Date: Thu 29/11/07

Tasks with Assignments

ID
Task Name
WorkDurationStartFinish% Work Complete
1      
2
Financial approval confirmed
0 hrs0 daysFri 01/06/07Fri 01/06/070%
3
Media Procurement
0 hrs130 daysFri 01/06/07Thu 29/11/070%
4
Write tender
0 hrs2 ewksFri 01/06/07Fri 15/06/070%
5
Sign off and circulate
0 hrs1 ewkFri 15/06/07Fri 22/06/070%
6
EU tender process
0 hrs4 monsFri 22/06/07Thu 11/10/070%
7
Select supplier
0 hrs1 ewkThu 11/10/07Thu 18/10/070%
8
Delivery lead time
0 hrs6 wksFri 19/10/07Thu 29/11/070%
9      
10
Bandwidth Procurement
0 hrs50 daysFri 01/06/07Thu 09/08/070%
11
9xT10Ks+maintenance
0 hrs50 daysFri 01/06/07Thu 09/08/070%
12
Write tender
0 hrs1 ewkFri 01/06/07Fri 08/06/070%
13
Sign off Req and circulate
0 hrs1 ewkFri 08/06/07Fri 15/06/070%
14
Responses returned
0 hrs3 wksFri 15/06/07Thu 05/07/070%
15
Decide and Order
0 hrs1 ewkThu 05/07/07Thu 12/07/070%
16
Delivery lead time
0 hrs4 wksFri 13/07/07Thu 09/08/070%
17
9x servers + maintenance
0 hrs35 daysFri 01/06/07Fri 20/07/070%
18
Get three quotes
0 hrs2 ewksFri 01/06/07Fri 15/06/070%
19
Decide and Sign-off requisition
0 hrs1 ewkFri 15/06/07Fri 22/06/070%
20
Delivery lead time
0 hrs4 ewksFri 22/06/07Fri 20/07/070%
21      
22
Robot Procurement - New Robot Req'd
0 hrs75 daysFri 01/06/07Fri 14/09/070%
23
Get up-to-date quote (single tender case)
0 hrs2 ewksFri 01/06/07Fri 15/06/070%
24
Sign-off requisition
0 hrs1 ewkFri 15/06/07Fri 22/06/070%
25
Get single tender case approved by DTI
0 hrs3 ewksFri 22/06/07Fri 13/07/070%
26
Place order
0 hrs1 ewkFri 13/07/07Fri 20/07/070%
27
Delivery lead time
0 hrs8 ewksFri 20/07/07Fri 14/09/070%