| 4.5 | |||||||||||||
| 1 | 4.5.1 | Preliminary Rollout Plan Established | DUE | 01-May-02 | |||||||||
| Description | Initial planning for the Grid rollout in the UK is undertaken. | ||||||||||||
| Metric | Rollout plan presented to PMB | ||||||||||||
| Risk and/or | |||||||||||||
| Dependency | |||||||||||||
| Status | Complete | Status Date | 05-Jun-02 | Modified Due Date | J | ||||||||
| 2 | 4.5.2 | Installation Instruction Set Tested | DUE | 01-Sep-02 | |||||||||
| Description | Preliminary instructions set for joining/using Grid should be tested on two category-2 sites. | ||||||||||||
| Metric | Tests completed on two sites. | ||||||||||||
| Risk and/or | |||||||||||||
| Dependency | |||||||||||||
| Status | Complete | Status Date | 05-Jun-02 | Modified Due Date | J | ||||||||
| 3 | 4.5.3 | Grid Rolled Out to Category-2 Sites | DUE | 01-Apr-03 | |||||||||
| Description | All interested category-2 sites should now be involved. | ||||||||||||
| Metric | Involvement of all interested category-2 sites. | ||||||||||||
| Risk and/or | |||||||||||||
| Dependency | |||||||||||||
| Status | Complete | Status Date | 10-Sep-02 | Modified Due Date | J | Link to map or news item | |||||||
| 4 | 4.5.4 | Grid rolled out to category-3 (turn-key) users | DUE | ||||||||||
| Description | By this time the UK Grid should be available to Turn-Key users according to the developed rollout | This milestone is deactivated as it falls in the GridPP2 | |||||||||||
| plan. | time-frame and is replaced by the GridPP2 planning | ||||||||||||
| (particularly the "production grid metrics") | |||||||||||||
| Metric | Number of institutes in the UK engaged. | ||||||||||||
| Risk and/or | |||||||||||||
| Dependency | |||||||||||||
| Status | Not started | Status Date | Modified Due Date | J | |||||||||