| 4.1 | ||||||||||
| 1 | 4.1.1 | 2002 BaBar common fund rebate is agreed. | DUE | 01-Apr-02 | ||||||
| Description | BaBar agrees that Tier-A hardware generates common-fund rebate | |||||||||
| Metric | Common fund rebate. | |||||||||
| Risk and/or | BaBar does not agree. | |||||||||
| Dependency | ||||||||||
| Status | Complete | Status Date | 05-Jun-02 | Modified Due Date | J | |||||
| 2 | 4.1.2 | New Tier-A hardware installed | DUE | 01-Oct-02 | ||||||
| Description | New Tier-A hardware installed and demonstrated to meet requirements. | |||||||||
| Metric | Hardware is tested at full capacity and available for use. | |||||||||
| Risk and/or | ||||||||||
| Dependency | ||||||||||
| Status | Complete | Status Date | 10-Sep-02 | Modified Due Date | J | Link to final version of JG's OC report. | ||||
| 3 | 4.1.3 | BaBar Successfully use Tier-A Hardware | DUE | 31-Dec-02 | ||||||
| Description | Tier-A hardware is successfully incorporated into BaBar production. | |||||||||
| Metric | BaBar using more than 80% of hardware reserved for its use. | |||||||||
| Risk and/or | ||||||||||
| Dependency | ||||||||||
| Status | Complete | Status Date | 10-Sep-02 | Modified Due Date | J | Link to final version of JG's OC report. | ||||
| 4 | 4.1.4 | 2003 BaBar common fund rebate is agreed. | DUE | 01-Apr-03 | ||||||
| Description | BaBar agrees that new Tier-A hardware generates common-fund rebate | |||||||||
| Metric | Common fund rebate. | |||||||||
| Risk and/or | BaBar does not agree. | |||||||||
| Dependency | ||||||||||
| Status | Complete | Status Date | Modified Due Date | J | ||||||
| 5 | 4.1.5 | 2003 Tier-A hardware installed | DUE | 01-Jun-03 | ||||||
| Description | 2003 Tier-A hardware installed and demonstrated to meet requirements. | Click here for changeform | ||||||||
| Delay of 3 months | ||||||||||
| No serious consequence | ||||||||||
| Metric | Hardware is tested at full capacity and available for use. | |||||||||
| Risk and/or | ||||||||||
| Dependency | ||||||||||
| Status | Complete | Status Date | Modified Due Date | J | ||||||
| 6 | 4.1.6 | BaBar Successfully use Tier-A Hardware | DUE | 30-Sep-03 | ||||||
| Description | Tier-A hardware is successfully incorporated into BaBar production. | |||||||||
| Metric | BaBar using more than 80% of hardware reserved for its use. | |||||||||
| Risk and/or | ||||||||||
| Dependency | ||||||||||
| Status | Complete | Status Date | Modified Due Date | J | ||||||
| 7 | 4.1.7 | 2004 BaBar common fund rebate is agreed. | DUE | 31-Mar-04 | ||||||
| Description | BaBar agrees that new Tier-A hardware generates common-fund rebate | |||||||||
| Metric | Common fund rebate. | |||||||||
| Risk and/or | BaBar does not agree. | |||||||||
| Dependency | ||||||||||
| Status | Complete | Status Date | Modified Due Date | J | Link to Tier-1 board minutes from May 13th 2004 | |||||
| 8 | 4.1.8 | New Tier-A hardware installed | DUE | 30-Sep-04 | ||||||
| Description | New Tier-A hardware installed and demonstrated to meet requirements. | See Q3 report. Report to T1 board. Q4 report | ||||||||
| Metric | Hardware is tested at full capacity and available for use. | |||||||||
| Risk and/or | ||||||||||
| Dependency | ||||||||||
| Status | Complete | Status Date | Modified Due Date | J | ||||||
| 9 | 4.1.9 | BaBar Successfully use Tier-A Hardware | DUE | |||||||
| Description | Tier-A hardware is successfully incorporated into BaBar production. | |||||||||
| This deliverable is deactivated and is | ||||||||||
| Metric | BaBar using more than 80% of hardware reserved for its use. | covered in the the GridPP2 planning. | ||||||||
| Risk and/or | ||||||||||
| Dependency | ||||||||||
| Status | Not started | Status Date | Modified Due Date | J | ||||||