| 3.3 | ||||||||||||||||
| 1 | 3.3.1 | PVSS Review & Development | DUE | 30-Sep-02 | ||||||||||||
| Description | Adapt & develop current PVSS system to the DATA Challenges & the developing MC production | |||||||||||||||
| system. Review the current PVSS based control system & compare with WP3 middleware | ||||||||||||||||
| Metric | Document and prototype | |||||||||||||||
| Risk and/or | ||||||||||||||||
| Dependency | ||||||||||||||||
| Status | Complete | Status Date | 10-Sep-02 | Modified Due Date | J | |||||||||||
| 2 | 3.3.2 | Monitoring Prototype | DUE | 31-Mar-03 | 3.3.2 | Monitoring Prototype | DUE | 31-Dec-02 | ||||||||
| Description | Initial development of Grid based monitoring and control system | Conclusion of 3.3.1 is not to use WP3 stuff. | Description | Introduce monitoring based on WP3 middleware (assumes WP3 APIs exist) & assess whether to | ||||||||||||
| Introduces the use of Work Flow Description Language | Click her for changeform | maintain current PVSS system. | ||||||||||||||
| Old deliverable is here ---> | ||||||||||||||||
| Metric | Demo in the UK | Conclusion of 3.3.1 was not to | Metric | Document and prototype | ||||||||||||
| use WP3 stuff so this redefined | ||||||||||||||||
| Risk and/or | 3.3.2 | Risk and/or | API's to WP3 are produced in time. | |||||||||||||
| Dependency | Dependency | |||||||||||||||
| Status | Complete | Status Date | 19-Mar-03 | Modified Due Date | J | Status | In Progress | Status Date | 17-Jan-03 | Modified Due Date | J | |||||
| 3 | 3.3.3 | First prototype of New Experimental System | DUE | 30-Sep-03 | 3.3.3 | First prototype of New Experimental System | DUE | 30-Jun-03 | ||||||||
| Description | Introduce monitoring of details of a running job. eg. run number. A first implementation of data | Description | Introduce monitoring of details of a running job eg. run number. A first implementation of online | |||||||||||||
| quality monitoring | Click her for changeform | histogram production. | ||||||||||||||
| Old deliverable is here ---> | ||||||||||||||||
| Metric | Demonstration of new system | Broadened scope somewhat as a | Metric | Demonstration of new system | ||||||||||||
| better understanding achieved. | ||||||||||||||||
| Risk and/or | Intoduces some delay | Risk and/or | ||||||||||||||
| Dependency | Dependency | |||||||||||||||
| Status | Complete | Status Date | Modified Due Date | J | Status | Not started | Status Date | Modified Due Date | J | |||||||
| 4 | 3.3.4 | Workflow Based Production System | DUE | 30-Apr-04 | 3.3.4 | Online Histogram Monitoring | DUE | 31-Dec-03 | ||||||||
| Description | Database powered production environment including online visualisation of workflow. | Click her for changeform | Description | Sophisticated online histogram production & data quality assurance. | ||||||||||||
| Old deliverable is here ---> | ||||||||||||||||
| Original idea now expressed in the | ||||||||||||||||
| Metric | Release of production version. | actual LHCb environment (Dirac) | Metric | Release of production version. | ||||||||||||
| Time frame now matches DC04 | ||||||||||||||||
| Risk and/or | Risk and/or | |||||||||||||||
| Dependency | Dependency | |||||||||||||||
| Status | Complete | Status Date | Modified Due Date | J | See 2004Q2 report. Deployed for DC04. | Status | Not started | Status Date | Modified Due Date | J | ||||||
| 5 | 3.3.5 | Interface to DIRAC | DUE | 30-Sep-04 | Click her for changeform | |||||||||||
| Description | Full integration with DIRAC services | |||||||||||||||
| Metric | Beta Release | |||||||||||||||
| Risk and/or | Ganga exists | |||||||||||||||
| Dependency | ||||||||||||||||
| Status | Complete | Status Date | Modified Due Date | J | Becomes 3.3.8 in GridPP2 ProjectMap | |||||||||||
| 6 | 3.3.6 | Full integration with DIRAC | DUE | Click her for changeform | ||||||||||||
| Description | Final version of Production Desktop and full integration into DIRAC | |||||||||||||||
| Metric | Final release; Document and demonstration | |||||||||||||||
| Risk and/or | ||||||||||||||||
| Dependency | ||||||||||||||||
| Status | Not started | Status Date | Modified Due Date | J | Becomes 3.3.9 in GridPP2 ProjectMap | |||||||||||
| 7 | ||||||||||||||||
| 8 | ||||||||||||||||
| 9 | ||||||||||||||||