| 2.6 | ||||||||
| 1 | 2.6.1 | Deliver WP6 Effort | DUE | on going | ||||
| Description | Deliver WP6 effort as contracted | |||||||
| Primarily a UK responsibility | ||||||||
| Metric | Cumulative Effort Delivered | |||||||
| Current Total | 149.20% | |||||||
| Current Threshold | 90% | |||||||
| Status | In Progress | Status Date | 05-Jun-02 | J | ||||
| 2 | 2.6.2 | Integration & Operation | DUE | 30-Apr-01 | ||||
| Description | D6.1 Testbed software integration process, operational policies and procedures report | |||||||
| Not primarily a UK responsibility but UK will contribute | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | None | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||
| 3 | 2.6.3 | Policies, evaluation and procedures | DUE | 30-Jun-01 | ||||
| Description | D6.2 Project release policy, definitions, evaluation targets and procedures | |||||||
| Not primarily a UK responsibility but UK will contribute | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | None | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||
| 4 | 2.6.4 | First project release | DUE | 30-Sep-01 | ||||
| Description | D6.3 First project release | |||||||
| Not primarily a UK responsibility but UK will contribute | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | Depends on first project release deliverables from middleware workpackages | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||
| 5 | 2.6.5 | First project release evaluation | DUE | 31-Dec-01 | ||||
| Description | D6.4 Evaluation of testbed operation | |||||||
| Not primarily a UK responsibility but UK will contribute | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | Depends on successful deployment of first project release | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||
| 6 | 2.6.6 | Second project release | DUE | 15-Jan-03 | ||||
| Description | D6.5 Second project release | |||||||
| Not primarily a UK responsibility but UK will contribute | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | Depends on second project release deliverables from middleware workpackages | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 06-Jan-03 | J | ||||
| 7 | 2.6.7 | Second project release evaluation | DUE | 01-Jun-03 | ||||
| Description | D6.6 Evaluation of testbed operation | |||||||
| Not primarily a UK responsibility but UK will contribute | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | Depends on successful deployment of second project release | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||
| 8 | 2.6.8 | Final project release | DUE | 30-Sep-03 | ||||
| Description | D6.7 Final project release | |||||||
| Not primarily a UK responsibility but UK will contribute | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | Depends on final project release deliverables from middleware workpackages | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||
| 9 | 2.6.9 | Final project release evaluation | DUE | 31-Dec-03 | ||||
| Description | D6.8 Final evaluation of testbed operation | |||||||
| Not primarily a UK responsibility but UK will contribute | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | Depends on successful deployment of second project release | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||