| 2.4 | ||||||||
| 1 | 2.4.1 | Deliver WP4 Effort | DUE | on going | ||||
| Description | Deliver WP4 effort as contracted | |||||||
| Primarily a UK responsibility | ||||||||
| Metric | Cumulative Effort Delivered | |||||||
| Current Total | 256.30% | |||||||
| Current Threshold | 90% | |||||||
| Status | In Progress | Status Date | 05-Jun-02 | J | ||||
| 2 | 2.4.2 | Technology review | DUE | 30-Apr-01 | ||||
| Description | D4.1 Report of current technology | |||||||
| Not primarily a UK responsibility but UK will contribute | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | None | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||
| 3 | 2.4.3 | Architecture | DUE | 30-Jun-01 | ||||
| Description | D4.2 Architectural design report and evaluation criteria | |||||||
| Not primarily a UK responsibility but UK will contribute | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | None | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||
| 4 | 2.4.4 | First project release | DUE | 30-Sep-01 | ||||
| Description | D4.3 Components and documentation for the first project release | |||||||
| Not primarily a UK responsibility but UK will contribute | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | None | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||
| 5 | 2.4.5 | Second project release | DUE | 15-Jan-03 | ||||
| Description | D4.4 Components and documentation for the second project release | |||||||
| Not primarily a UK responsibility but UK will contribute | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | EDG may not stay with LCFG in the longer term | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 06-Jan-03 | J | ||||
| 6 | 2.4.6 | Final project release | DUE | 30-Sep-03 | ||||
| Description | D4.5 Components and documentation for the final project release | |||||||
| Not primarily a UK responsibility but UK will contribute | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | EDG may not stay with LCFG in the longer term | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||
| 7 | 2.4.7 | Evaluation | DUE | 31-Dec-03 | ||||
| Description | D4.6 Final evaluation report | |||||||
| Not primarily a UK responsibility but UK will contribute | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | Depends on successful delivery of project releases | |||||||
| Dependency | EDG may not stay with LCFG in the longer term | |||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||