| 2.3 | ||||||||
| 1 | 2.3.1 | Deliver WP3 Effort | DUE | on going | ||||
| Description | Deliver WP3 effort as contracted | |||||||
| Primarily a UK responsibility | ||||||||
| Metric | Cumulative Effort Delivered | |||||||
| Current Total | 146.80% | |||||||
| Current Threshold | 90% | |||||||
| Status | In Progress | Status Date | 05-Jun-02 | J | ||||
| 2 | 2.3.2 | Technology review | DUE | 12-Dec-01 | ||||
| Description | D3.1 Current Technology Evaluation | |||||||
| Primarily a UK responsibility | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | None | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||
| 3 | 2.3.3 | Architecture | DUE | 30-Sep-01 | ||||
| Description | D3.2 Architecture Design | |||||||
| Primarily a UK responsibility | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | None | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||
| 4 | 2.3.4 | First Prototype | DUE | 30-Sep-01 | ||||
| Description | D3.3 First Prototype | |||||||
| Primarily a UK responsibility | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | None | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||
| 5 | 2.3.5 | Second Prototype | DUE | 15-Jan-03 | ||||
| Description | D3.4 Second Prototype | |||||||
| Primarily a UK responsibility | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | Has significant input from core eScience project working with EDG | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 06-Jan-03 | J | ||||
| 6 | 2.3.6 | Final Prototype | DUE | 30-Sep-03 | ||||
| Description | D3.5 Final Prototype | |||||||
| Primarily a UK responsibility | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | Has significant input from core eScience project working with EDG | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||
| 7 | 2.3.7 | Evaluation | DUE | 31-Dec-03 | ||||
| Description | D3.6 Final Evaluation Report | |||||||
| Primarily a UK responsibility | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | Depends on successful delivery of project releases | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||