| 2.1 | ||||||||
| 1 | 2.1.1 | Deliver WP1 Effort | DUE | on going | ||||
| Description | Deliver WP1 effort as contracted | |||||||
| Primarily a UK responsibility | ||||||||
| Metric | Cumulative Effort Delivered | |||||||
| Current Total | 215.00% | |||||||
| Current Threshold | 90% | |||||||
| Status | In Progress | Status Date | 05-Jun-02 | J | ||||
| 2 | 2.1.2 | Install and Test | DUE | on going | ||||
| Description | Install and test EDG WP1 software | |||||||
| UK responsibility as part of an EDG-wide effort | ||||||||
| Metric | Latest WP1 software working in the UK | |||||||
| (Use 1 for 'yes' and 0 for 'no' in Current Total field below) | ||||||||
| Current Total | 1 | |||||||
| Current Threshold | 1 | |||||||
| Status | In Progress | Status Date | 05-Jun-02 | J | ||||
| 3 | 2.1.3 | Technology Assessment | DUE | 31-Mar-01 | ||||
| Description | D1.1 Report of current technology | |||||||
| Not primarily a UK responsibility but UK will contribute | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | ||||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||
| 4 | 2.1.4 | Requirements & Architecture | DUE | 30-Jun-01 | ||||
| Description | D1.2 Detailed report on requirements, architectural design, and evaluation criteria | |||||||
| Not primarily a UK responsibility but UK will contribute | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | ||||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||
| 5 | 2.1.5 | First Project Release | DUE | 30-Sep-01 | ||||
| Description | D1.3 Components and documentation for the first Project Release | |||||||
| Not primarily a UK responsibility but UK will contribute | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | None | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||
| 6 | 2.1.6 | Co-allocation & Parallel Jobs | DUE | 30-Jun-02 | ||||
| Description | D1.4 Co-allocation and parallel job partitioning architecture | |||||||
| Not primarily a UK responsibility but UK will contribute | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | None | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||
| 7 | 2.1.7 | Second Project release | DUE | 15-Jan-03 | ||||
| Description | D1.5 Components and documentation for the second Project Release | |||||||
| Not primarily a UK responsibility but UK will contribute | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | None | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 06-Jan-03 | J | ||||
| 8 | 2.1.8 | Final Project Release | DUE | 30-Sep-03 | ||||
| Description | D1.6 Components and documentation for the final Project Release | |||||||
| Not primarily a UK responsibility but UK will contribute | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | None | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||
| 9 | 2.1.9 | Evaluation | DUE | 31-Dec-03 | ||||
| Description | D1.7 Final evaluation report | |||||||
| Not primarily a UK responsibility but UK will contribute | ||||||||
| Metric | Delivered on time and formally accepted by EDG | |||||||
| Risk and/or | Depends on successful delivery of project releases | |||||||
| Dependency | ||||||||
| Status | Complete | Status Date | 05-Jun-02 | J | ||||