1.4
1 1.4.1 Middleware Components Defined DUE 01-Dec-02 Corresponds to the subsequently definded LCG deliverable
Description As for applications environments, there are various competing sources of the different  1.3.2.8
Grid middleware components. A single set must be defined for LCG use.
 
Metric Single set of components defined.
 
Risk and/or It is hoped that GLUE will produce agreement on middleware    
Dependency      
Status Complete Status Date 09-Sep-02 Modified Due Date   J
2 1.4.2 Testing and Validation Process Defined DUE 01-Feb-03
Description Testing and Validation Process Defined
 
 
Metric Definition established
 
Risk and/or      
Dependency      
Status Complete Status Date 09-Sep-02 Modified Due Date   J CLICK HERE AND THEN LOOK AT WG4 DOCUMENT Sec 2.3
3 1.4.3 Middleware Components Assembled, Tested and Available DUE 01-Apr-03
Description The middleware components identified in 1.3.1 are available in an agreed location for LCG, e.g.
the repository identified in 1.1.1
 
Metric Middleware Components Assembled, Tested and Available
 
Risk and/or      
Dependency      
Status Complete Status Date 09-Sep-02 Modified Due Date   J
4 1.4.4 Full Test Suite Completed DUE 01-Jun-03
Description Full Test Suite Completed
 
 
Metric Full Test Suite Completed
 
Risk and/or      
Dependency      
Status Complete Status Date 09-Sep-02 Modified Due Date   J TC email Feb 5th 2004
5 1.4.5 Future Milestones DUE 01-Sep-03
Description Milestones for the remainder of the LCG project are yet to be defined
 
 
Metric Milestones defined
 
Risk and/or      
Dependency       See new milestones below
Status Complete Status Date 22-Apr-03 Modified Due Date   J
6 1.4.6 Draft definition of Middleware to be used for LCG-3 service DUE  
Description An initial definition of the middleware to be used for LCG-3 is available following discussions with
the participating sites.
This milestone corresponds to milestone 4.961 of the LCG plan.
Metric  
 
Risk and/or      
Dependency      
Status Delayed Status Date   Modified Due Date   J See TC email 30-Jan-04 and in May 04
7 1.4.7 Final definition of Middleware to be used for LCG-3 service DUE  
Description Th middleware to be used for the LCG-3 service has been agreed with all partners and the
definition has been published and agreed by SC2.
This milestone corresponds to milestone 1.3.5.5 of the LCG plan.
Metric  
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
8 1.4.8 Agreed LCG-3 middleware delivered for deployment DUE  
Description The middleware of 1.4.7 is available in an agreed location ready for deployment on the
LCG-3 service.
This milestone corresponds to milestone 1.3.5.6 of the LCG plan.
Metric  
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J
9 1.4.9 Updated PASTA Technology Review Complete DUE   Deliverable deactivated as it falls in the GridPP2
Description The 2004 version of the PASTA reports has been published. timeframe.
 
This milestone corresponds to milestone 1.3.4.4 of the LCG plan.
Metric  
 
Risk and/or      
Dependency      
Status Not started Status Date   Modified Due Date   J