| 1.4 | ||||||||||||||
| 1 | 1.4.1 | Middleware Components Defined | DUE | 01-Dec-02 | Corresponds to the subsequently definded LCG deliverable | |||||||||
| Description | As for applications environments, there are various competing sources of the different | 1.3.2.8 | ||||||||||||
| Grid middleware components. A single set must be defined for LCG use. | ||||||||||||||
| Metric | Single set of components defined. | |||||||||||||
| Risk and/or | It is hoped that GLUE will produce agreement on middleware | |||||||||||||
| Dependency | ||||||||||||||
| Status | Complete | Status Date | 09-Sep-02 | Modified Due Date | J | |||||||||
| 2 | 1.4.2 | Testing and Validation Process Defined | DUE | 01-Feb-03 | ||||||||||
| Description | Testing and Validation Process Defined | |||||||||||||
| Metric | Definition established | |||||||||||||
| Risk and/or | ||||||||||||||
| Dependency | ||||||||||||||
| Status | Complete | Status Date | 09-Sep-02 | Modified Due Date | J | CLICK HERE AND THEN LOOK AT WG4 DOCUMENT Sec 2.3 | ||||||||
| 3 | 1.4.3 | Middleware Components Assembled, Tested and Available | DUE | 01-Apr-03 | ||||||||||
| Description | The middleware components identified in 1.3.1 are available in an agreed location for LCG, e.g. | |||||||||||||
| the repository identified in 1.1.1 | ||||||||||||||
| Metric | Middleware Components Assembled, Tested and Available | |||||||||||||
| Risk and/or | ||||||||||||||
| Dependency | ||||||||||||||
| Status | Complete | Status Date | 09-Sep-02 | Modified Due Date | J | |||||||||
| 4 | 1.4.4 | Full Test Suite Completed | DUE | 01-Jun-03 | ||||||||||
| Description | Full Test Suite Completed | |||||||||||||
| Metric | Full Test Suite Completed | |||||||||||||
| Risk and/or | ||||||||||||||
| Dependency | ||||||||||||||
| Status | Complete | Status Date | 09-Sep-02 | Modified Due Date | J | TC email Feb 5th 2004 | ||||||||
| 5 | 1.4.5 | Future Milestones | DUE | 01-Sep-03 | ||||||||||
| Description | Milestones for the remainder of the LCG project are yet to be defined | |||||||||||||
| Metric | Milestones defined | |||||||||||||
| Risk and/or | ||||||||||||||
| Dependency | See new milestones below | |||||||||||||
| Status | Complete | Status Date | 22-Apr-03 | Modified Due Date | J | |||||||||
| 6 | 1.4.6 | Draft definition of Middleware to be used for LCG-3 service | DUE | |||||||||||
| Description | An initial definition of the middleware to be used for LCG-3 is available following discussions with | |||||||||||||
| the participating sites. | ||||||||||||||
| This milestone corresponds to milestone 4.961 of the LCG plan. | ||||||||||||||
| Metric | ||||||||||||||
| Risk and/or | ||||||||||||||
| Dependency | ||||||||||||||
| Status | Delayed | Status Date | Modified Due Date | J | See TC email 30-Jan-04 | and in May 04 | ||||||||
| 7 | 1.4.7 | Final definition of Middleware to be used for LCG-3 service | DUE | |||||||||||
| Description | Th middleware to be used for the LCG-3 service has been agreed with all partners and the | |||||||||||||
| definition has been published and agreed by SC2. | ||||||||||||||
| This milestone corresponds to milestone 1.3.5.5 of the LCG plan. | ||||||||||||||
| Metric | ||||||||||||||
| Risk and/or | ||||||||||||||
| Dependency | ||||||||||||||
| Status | Not started | Status Date | Modified Due Date | J | ||||||||||
| 8 | 1.4.8 | Agreed LCG-3 middleware delivered for deployment | DUE | |||||||||||
| Description | The middleware of 1.4.7 is available in an agreed location ready for deployment on the | |||||||||||||
| LCG-3 service. | ||||||||||||||
| This milestone corresponds to milestone 1.3.5.6 of the LCG plan. | ||||||||||||||
| Metric | ||||||||||||||
| Risk and/or | ||||||||||||||
| Dependency | ||||||||||||||
| Status | Not started | Status Date | Modified Due Date | J | ||||||||||
| 9 | 1.4.9 | Updated PASTA Technology Review Complete | DUE | Deliverable deactivated as it falls in the GridPP2 | ||||||||||
| Description | The 2004 version of the PASTA reports has been published. | timeframe. | ||||||||||||
| This milestone corresponds to milestone 1.3.4.4 of the LCG plan. | ||||||||||||||
| Metric | ||||||||||||||
| Risk and/or | ||||||||||||||
| Dependency | ||||||||||||||
| Status | Not started | Status Date | Modified Due Date | J | ||||||||||