1.3
1 1.3.1 Joint LCG/EDG cluster increased to 200 nodes DUE 07-Jul-02
Description Contributed funding allows the acquisition of additional hardware components (CPU and disk
servers) to increase the size of the LCG/EDG cluster to 200 nodes.
 
Metric 200 Node installed.
 
Risk and/or      
Dependency      
Status Complete Status Date 09-Sep-02 Modified Due Date   J Note: Nodes installed with other funding. Proposal to re-deploy GridPP funding (see link).
2 1.3.2 Joint LCG/EDG Production Testbed Completed DUE 01-Nov-02
Description The EDG Grid middleware is installed and running on the LCG/EDG cluster of 1.3.1
 
 
Metric The EDG Grid middleware is installed and running on the LCG/EDG cluster of 1.3.1
 
Risk and/or Installation does not scale to 200 nodes.    
Dependency       Risk was precient! Installation did not scale but the ATLAS/CMS
Status Complete Status Date 09-Sep-02 Modified Due Date   J tests were performed so milestone was essentially done.
3 1.3.3 LCG-1 Cluster increased to 400 nodes DUE 01-May-03
Description As 1.3.1 for expansion to 400 nodes.
 
 
Metric 400 nodes installed
 
Risk and/or Scaling problems    
Dependency SW stability    
Status Complete Status Date 09-Sep-02 Modified Due Date   J Email from TC on 12/Sep/03
4 1.3.4 LCG-1 Production Cluster Operational DUE 01-Jul-03
Description The middleware components of 1.4.1 installed and running on the LCG-1 cluster (1.3.3)
Aligned with LCG deliverable  1.2.4.2.3 (2.560)
 
Metric The middleware components of 1.4.1 installed and running on the LCG-1 cluster (1.3.3)
 
Risk and/or Depends on cluster  1.3.3  
Dependency Depends on middleware components  1.2.1   Email from TC on 12/Sep/03
Status Complete Status Date 09-Sep-02 Modified Due Date   J Link To LCG Press release
5 1.3.5 Cluster Automation Complete DUE 30-Mar-03
Description Automated tools for installation of LCG-1 cluster available.
Precise set of tools depends on EDG and other developments (c.f. 1.3.1), but tools should adhere 
to principles of the EDG WP4 architecture and design document.
Metric As above
 
Risk and/or      
Dependency      
Status Complete Status Date 09-Sep-02 Modified Due Date   J
6 1.3.6 Future Milestones DUE 01-Sep-03
Description Milestones for the remainder of the LCG project are yet to be defined
 
 
Metric Milestones defined
 
Risk and/or      
Dependency      
Status Complete Status Date 09-Sep-02 Modified Due Date   J
7 1.3.7 CASTOR production system ready for deployment DUE 01-Dec-04 Click her for changeform
Description Improved CASTOR system with pluggable schedular and high rate request handling available
 
 
Metric LCG 1.2.1.1.3/2.519 marked complete
 
Risk and/or       Email from TC Dec/04. Castor report to
Dependency       SC2 (not public yet).
Status Complete Status Date   Modified Due Date   J
8 1.3.8 Fabric Management with EDG Tools DUE 30-Apr-04
Description CERN fabric fully managed with EDG tools
 
 
Metric Fabric is managed with EDG WP4 product
 
Risk and/or      
Dependency      
Status Complete Status Date   Modified Due Date   J
9 1.3.9 Advanced Fabric Management DUE 01-Sep-04
Description Advanced Fabric Management tools are implemented on top of the EDG tools
 
 
Metric  
 
Risk and/or      
Dependency      
Status Complete Status Date   Modified Due Date   J
# 1.3.10 LCG2 definition of CPU and Storage Architectures DUE   Click here for changeform
Description The CPU and Storage architectures for LCG-2 are defined. This combines LCG milestones
1.2.1.3.3/2.524 and 1.2.4.1/2.564
 
Metric 1.2.1.3.3/2.524 and 1.2.4.1/2.564 marked complete
 
Risk and/or      
Dependency       Deactivated and to be included in GridPP2
Status Not Started Status Date   Modified Due Date   J
# 1.3.11 Backbone upgrade to 10GB DUE 01-Dec-05 Click here for changeform
Description First phase of backbone upgrade is complete (to 10GB)
LCG milestone 1.2.5.9/2.582
 
Metric 1.2.5.9/2.582 marked complete
 
Risk and/or      
Dependency      
Status Complete Status Date   Modified Due Date   J