1.2
1 1.2.1 Software Process Infrastructure in place DUE 07-Jul-02
Description The LCG project requires an agreed software process and appropriate support tools, including
repository, configuration and release management tools. The components of the infrastructure
are to be defined by an RTAG created for this purpose.
Metric Agreed services are up and running by due date
 
Risk and/or      
Dependency      
Status Complete Status Date 09-Sep-02 Modified Due Date   J
2 1.2.2 Prototype Hybrid Datastore completed DUE 30-Nov-02
Description First version of hybrid eventstore released. Limited functionality only required and expected to
be used by experts only.
 
Metric Functionality, interfaces and documentation delivered according to requirements set at June
persistency workshop.
Risk and/or      
Dependency      
Status Complete Status Date 09-Sep-02 Modified Due Date   J
3 1.2.3 LCG-1 Applications Environment Defined DUE 01-Mar-03
Description Each LHC experiment has a distinct application environment and other environment components This is roughly equiverlent to 1.1.4.3 in the LCG planning
have been produced by IT. A common set must be selected to serve as the base for development (which post dated this ProjectMap definition).
and for testing on the LCG prototypes The SEAL project incoporates our milestone. Thus,
Metric Report from PEB by due date we take the release of SEAL V1 as the completion of
  our milestone but we will define future milestones to 
Risk and/or       include the rest of the SEAL project
Dependency      
Status Complete Status Date 27-Feb-03 Modified Due Date   J
4 1.2.4 LCG-1 Applications Environment Software Available DUE 31-Jul-03
Description Once the different components of the application environment have been defined, they must be
collected and made available centrally.
This is part of LCG deliverable M1.1
Metric software components identified in 1.2.3 available in software repository of 1.2.1
 
Risk and/or   1.2.1  
Dependency   1.2.3  
Status Complete Status Date 09-Sep-02 Modified Due Date   J See this link also
5 1.2.5 General Release Hybrid Event Store DUE 01-Jul-03
Description A more functional and robust (but not yet complete) version of the persistency framework. Complete on June 30th. See P15 of the link to Torre's GridPP7 Talk.
This will be a release offering basic hybrid persistency services, properly documented and For more details, see other GridPP7 talks.
packaged for general use by the experiments. This is LCG M1.2 deliverable.
Metric Release made by due date.
LHC experiments able to make use of it.
Risk and/or      
Dependency      
Status Complete Status Date 09-Sep-02 Modified Due Date   J
6 1.2.6 Future Milestones DUE 01-Sep-03
Description Milestones for the remainder of the LCG project are yet to be defined
 
 
Metric Milestones defined
 
Risk and/or      
Dependency      
Status Complete Status Date 09-Sep-02 Modified Due Date   J Email from TC on 3/Nov/03 has details. Yet to be implemented in ProjectMap
7 1.2.7 Pool implementation of conditions DB DUE 31-Mar-04
Description LCG 1.1.2.1/1.12. Full public release of Pool backend to the conditions database
 
 
Metric LCG 1.1.2.1/1.12 marked complete
 
Risk and/or      
Dependency      
Status Complete Status Date 09-Sep-02 Modified Due Date   J
8 1.2.8 Pool meets scalability requirements DUE 31-Oct-04
Description LCG 1.1.2.1/1.122. Pool meets scalability requirements
 
 
Metric LCG 1.1.2.1/1.122 marked complete
 
Risk and/or      
Dependency      
Status Complete Status Date 09-Sep-02 Modified Due Date   J
9 1.2.9 Production Release of Simulation Framework DUE  
Description LCG 1.1.5.1/1.147. First generic simulation framework production release This deliverable is deactivated as it falls within the GridPP2
  time frame. It was originally due in Oct 2004 but has been 
  only partially satisfied by the Prototype Relase currently
Metric LCG 1.1.5.1/1.147 marked complete available (Dec 2004). This whole area of the LCG programme
  was delayed through lack of manpower.
Risk and/or       (Emaill from Tony Cass, 17/Dec/2004)
Dependency      
Status Not started Status Date 09-Sep-02 Modified Due Date   J
# 1.2.10 Final Physics Validation DUE   This deliverable is deactivated as it falls within the GridPP2
Description LCG 1.1.5.4/1.148. Final physics validation document complete time frame.
  The related LCG deliverable is now scheduled to be due at
  the end of June 2005.
Metric LCG 1.1.5.4/1.148 marked complete
 
Risk and/or      
Dependency      
Status Not started Status Date 09-Sep-02 Modified Due Date   J