| ID | Name | GridPP | LCG | EDG | Apps | Infrast. | Interop. | |||||||||||||
| Li | Im | Risk | Li | Im | Risk | Li | Im | Risk | Li | Im | Risk | Li | Im | Risk | Li | Im | Risk | |||
| R1 | Recruitment/retention difficulties | 3 | 2 | 6 | 2 | 2 | 4 | 2 | 2 | 4 | 2 | 2 | 4 | |||||||
| R2 | Sudden loss of key staff | 1 | 4 | 4 | 1 | 3 | 3 | 1 | 3 | 3 | 1 | 3 | 3 | |||||||
| R3 | Minimal Contingency | 1 | 2 | 2 | 2 | 2 | 4 | 1 | 2 | 2 | ||||||||||
| R4 | GridPP deliverables late | 1 | 3 | 3 | 4 | 2 | 8 | |||||||||||||
| R5 | Sub-components not delivered to project | 2 | 4 | 8 | 2 | 3 | 6 | 2 | 3 | 6 | 2 | 4 | 8 | 2 | 3 | 6 | ||||
| R6 | Non take-up of project results | 2 | 1 | 2 | 2 | 3 | 6 | 1 | 4 | 4 | ||||||||||
| R7 | Change in project scope | 1 | 1 | 1 | 2 | 2 | 4 | 1 | 1 | 1 | ||||||||||
| R8 | Bad publicity | 2 | 2 | 4 | 1 | 3 | 3 | 1 | 3 | 3 | ||||||||||
| R9 | No publicity | 1 | 1 | 1 | ||||||||||||||||
| R10 | External software dependence | 2 | 3 | 6 | 2 | 4 | 8 | 1 | 4 | 4 | 3 | 2 | 6 | |||||||
| R11 | Lack of monitoring of staff | 1 | 2 | 2 | 2 | 2 | 4 | 2 | 3 | 6 | 1 | 2 | 2 | |||||||
| R12 | Withdrawal of an experiment | 1 | 4 | 4 | 1 | 4 | 4 | 1 | 2 | 2 | ||||||||||
| R13 | Lack of cooperation between Tier centres | 1 | 4 | 4 | 1 | 2 | 2 | |||||||||||||
| R14 | Scalablity problems | 1 | 3 | 3 | 2 | 3 | 6 | 1 | 3 | 3 | ||||||||||
| R15 | Software maintainability problems | 2 | 2 | 4 | 1 | 3 | 3 | |||||||||||||
| R16 | Technology shifts | 1 | 3 | 3 | 1 | 4 | 4 | 1 | 3 | 3 | 2 | 3 | 6 | |||||||
| R17 | Repitition of research | 3 | 2 | 6 | ||||||||||||||||
| R18 | Lack of funding to meet LCG PH-1 goals | 1 | 3 | 3 | ||||||||||||||||
| R19 | Adequate persistency solution not ready | 1 | 3 | 3 | ||||||||||||||||
| R20 | Conflicting software requirements | 4 | 1 | 4 | 2 | 2 | 4 | |||||||||||||
| R21 | Tier-A hardware fails to meet requirements | 1 | 3 | 3 | ||||||||||||||||
| R22 | Other Hardware fails to meet requirements | 1 | 1 | 1 | ||||||||||||||||
| R23 | Hardware physical risk (large scale) | 1 | 4 | 4 | ||||||||||||||||
| R24 | Hardware physical risk (small scale) | 2 | 2 | 4 | ||||||||||||||||
| R25 | Hardware procurement problems | 2 | 2 | 4 | ||||||||||||||||
| R26 | LAN Bottlenecks | 2 | 1 | 2 | ||||||||||||||||
| R27 | Tier-2 organisation fails | 2 | 2 | 4 | ||||||||||||||||
| R28 | Tier-2 hardware not used as planned | 2 | 1 | 2 | ||||||||||||||||
| R29 | SYSMAN effort inadequate | 2 | 3 | 6 | ||||||||||||||||
| R30 | Firewalls interfere with Grid | 1 | 3 | 3 | ||||||||||||||||
| R31 | Inablility to establish trust relationships | 2 | 2 | 4 | ||||||||||||||||
| R32 | Security inadequate to operate Grid | 3 | 3 | 9 | ||||||||||||||||
| R33 | GGF does not establish standards | 1 | 3 | 3 | ||||||||||||||||
| R34 | Minimal open source code development | 2 | 2 | 4 | ||||||||||||||||
| R35 | Failure of international cooperation | 3 | 2 | 6 | 1 | 4 | 4 | |||||||||||||
| R36 | e-Science and GridPP divergence | 2 | 2 | 4 | ||||||||||||||||
| R37 | Institutes do not embrace Grid | 1 | 3 | 3 | ||||||||||||||||
| R38 | Grid is not stable enough for use | 1 | 3 | 3 | ||||||||||||||||
| R39 | Delay of the LHC | 2 | 2 | 4 | ||||||||||||||||
| R40 | Lack of future funding | 1 | 4 | 4 | 2 | 2 | 4 | |||||||||||||
| R41 | Network backbone failure | 0 | 4 | 0.4 | ||||||||||||||||
| R42 | Network backbone bottleneck | 1 | 2 | 2 | ||||||||||||||||