J 3.1 ATLAS     Status Date 01-Apr-08     90 days
Owner: Roger Jones
Number Title Due Status Links More…
1 3.1.1 A0 Release of GANGA-based Monte Carlo submission system. 01-Jan-05 Complete I I
I
Metric  Software release with latest GANGA version including  AMI and Don Quiojte plug-ins. A.Tan   I      
Risk/Dep   [1]                  
History   [2]                  
2 3.1.2 A2 First release of ATLANTIS plug-in.  01-Jan-07 Complete I  
I
Metric  Software is released and events are produced. A.Tan          
Risk/Dep                     
History  ChangeForm1[3] ChangeForm2[4]                
3 3.1.3 A1 Refactored ATLAS production system integrated with EGEE middleware 01-Mar-06 Complete    
I
Metric  Software released and events production on EGEE. F. Brochu        
Risk/Dep                     
History  ChangeForm1[5]                  
4 3.1.4 A3 Grid-enabled Real Time Testing release.  01-Jan-06 Complete I  
I Roger to provide link (email 29/Jan/06)
Metric  Software release Rybkine          
Risk/Dep                     
History                     
5 3.1.5 A4 Kit installation and ADA package management service release. 01-Jan-06 Complete I  
I
Metric  . Integration, validation and production on latest LCG release (at least 10 adoptors) Rybkine          
Risk/Dep                     
History  ChangeForm1[6]                  
6 3.1.6 A5 ATLANTIS Grid usage in 'harvesting' mode for DC3 data. 01-Apr-06 Complete I I
I Roger to provide link (email 29/Jan/06)
Metric  Software release and demosntration. A.Tan          
Risk/Dep                     
History                     
7 3.1.7 A6 Distributed analysis using LCG/EGEE release in DC3. 01-Jul-06 Complete I  
I
Metric  Demonstration and at leasat 10 adopters. Brochu/Tan          
Risk/Dep                     
History                     
8 3.1.8 A8 ATLANTIS scripting/CLI support; preview facility; data discovery. 01-Oct-06 Complete I  
I Detailed comments in 06Q4 report
Metric  Software release A.Tan          
Risk/Dep                     
History                     
9 3.1.9 A7 Distributed analysis and production in DC4/Commissioning run.  01-Oct-07 In Progress    
I Not completed because of shift in FDR (now the combined test) to Feb-May 08
Metric  Analysis job submission with =>90% success rate. Brochu/Tan          
Risk/Dep                     
History  ChangeForm1[7] ChangeForm1[8]                
10 3.1.10 A10 Integration and validation of latest LCG release. 01-Jul-07 Complete I  
I
Metric  Document Brochu           
Risk/Dep                     
History                     
11 3.1.11 A11 Revised production and analysis tools.  01-Jul-07 Not Started    
I Depended on 3.1.9
Metric  Demonstration of of production-quality - minimum 98% success rate MC production Brochu/Tan          
Risk/Dep                     
History                     
12 3.1.12     Not Started    
I
Metric    A.Tan          
Risk/Dep                     
History  ChangeForm1[9]                  
13 3.1.13 A12 Final release of Grid analysis and production tools for data-taking. 31-Aug-07 Not Started    
I Depended on 3.1.9
Metric  Final software release Brochu/Tan          
Risk/Dep                     
History                     
14 3.1.14          
I
Metric               
Risk/Dep                     
History                     
15 3.1.15          
I
Metric               
Risk/Dep                     
History                     
01-Jan-05 01-Oct-04
01-Mar-06 01-Jan-05
01-Jan-06 01-Apr-05
01-Jan-06 01-Jul-05
01-Apr-06 01-Oct-05
01-Jul-06 01-Jan-06
01-Oct-07 01-Apr-06
01-Oct-06 01-Jul-06
01-Oct-06
01-Jan-07
01-Apr-07
01-Jul-07

[1]
Fill this in with code from Risk Register or use comments to note particular risks or dependencies
[2]
Links to ChangeForms if necessary
[3]
Links to ChangeForms if necessary
[4]
Links to ChangeForms if necessary
[5]
Links to ChangeForms if necessary
[6]
Links to ChangeForms if necessary
[7]
Links to ChangeForms if necessary
[8]
Links to ChangeForms if necessary
[9]
Links to ChangeForms if necessary