J 2.6 Networking     Status Date 01-Apr-08     90 days
Owner: Pete Clarke
Number Title Due Date Status Links More…
1 2.6.1 D2.1 UKLight Connectivity 01-Oct-04 Complete I  
I
Metric  Static light-path connectivity to CERN and FNAL            
Risk/Dep   [1]                  
History   [2]                  
2 2.6.2 D2.2 UKLight Basic Service 01-Mar-05 Complete I  
I
Metric  Demonstration of basic light-path switching services for data transport - 1 experiment  (CERN or FNAL) at ~ 1 Gbit/s         
Risk/Dep   [3]                  
History  Note: Used by SC2 and SC3 rather than an "Experiment". But this is in the spirit.[4]                  
3 2.6.3 D2.3 UKLight Developed Service 01-Sep-05 Complete I  
I Experiment demos are evidence. See email RM 19/Dec/05
Metric  Demonstration of light-path switching services for data transport -  >= 2 experiment (CERN or FNAL) at > 1 Gbit/s        
Risk/Dep                     
History                     
4 2.6.4 D2.4 High Performance Transport - Advanced Protocols 01-Sep-05 Complete I  
I See footnote [2] to deliverable table in logbook
Metric  Demo of multi Gbits/s (with goal of > 5 Gbit/s) transport with one or more advanced protocols, (to include a UDP blast).         
Risk/Dep                     
History                     
5 2.6.5 D2.5 Showcase Event 01-Mar-06 Complete    
I
Metric  A significant contribution to at least one showcase venue (SC2004, IGRID, CHEP)             
Risk/Dep                     
History                     
6 2.6.6 D2.6 UKLight/High Performance Transport Integration 01-Sep-06 Complete    
I
Metric  Integration of UK Tier1/2 sites with UKLIGHT/SuperJANET-5 architecture             
Risk/Dep                     
History                     
7 2.6.7 D2.7 Showcase Event 01-Mar-07 Complete I  
I
Metric  A significant contribution to a 2nd showcase venue (SC2004, IGRID, CHEP)             
Risk/Dep                     
History                     
8 2.6.8 D2.8 UKLight-GLIF 01-Mar-07 Complete I  
I
Metric  A significant contribution to enablement of GLIF            
Risk/Dep                     
History                     
9 2.6.9 D2.9 Strategic Report 31-Aug-07 In Progress    
I Still in progress -08Q1
Metric  Strategic report describing the benefits of hybrid service networking to particle physics            
Risk/Dep                     
History                     
10 2.6.10 D3.1 SLA/PPNCG Activity-1: Monitoring Deployment Ongoing OK    
I
Metric  Monitoring at GridPP sites is compliant with JRA4; Level-2 milestones achieved. OK OK        
Risk/Dep                     
History  Email RM 21/6/05 Email RM 29/11/05                
11 2.6.11 D3.2 SLA/PPNCG Activity-2: Network Consultancy to GridPP Ongoing OK    
I
Metric  Respond in a timely manner to requests. Quarterly reports document 2 actions/year 6 6        
Risk/Dep                     
History  Email RM 21/6/05 Email RM 29/11/05                
12 2.6.12 D3.3 SLA/PPNCG Activity-3: Other PPNCG Support Tasks Ongoing OK    
I
Metric  Respond in a timely manner to requests. Quarterly reports document actions. OK OK        
Risk/Dep                     
History  Email RM 29/11/05                  
13 2.6.13 D4.1: Strategic Relationships Ongoing OK    
I
Metric  Engagement with at least 6 relevent external bodies (UK RPANS, UKERNA, DANTE, Internet2, Abilene, StarLight, GLIF) 6 8        
Risk/Dep                     
History  Email RM 21/6/05 Email RM 29/11/05                
14 2.6.14          
I
Metric               
Risk/Dep                     
History                     
15 2.6.15          
I
Metric               
Risk/Dep                     
History                     

[1]
Fill this in with code from Risk Register or use comments to note particular risks or dependencies
[2]
Links to ChangeForms if necessary
[3]
Fill this in with code from Risk Register or use comments to note particular risks or dependencies
[4]
Links to ChangeForms if necessary