J
2.2
Storage
Status Date
01-Apr-08
90
days
Owner:
Jens Jensen
Number
Title
Due Date
Status
Links
More…
1
2.2.1
GS: Release of GS integrating with LCG3 at UK sites.
01-Feb-05
Complete
I
I
Metric
Software release.
Risk/Dep
[1]
History
[2]
2
2.2.2
LSM: Release of LSM integrating with LCG3 at UK sites.
01-Feb-05
Complete
I
I
Metric
Software release.
Risk/Dep
[3]
History
[4]
3
2.2.3
GS: Software prototype/bugfix release integrating with EGEE DJRA1.3.
01-Apr-05
Complete
I
I
Metric
Software release.
Risk/Dep
History
4
2.2.4
LSM:Software prototype/bugfix release integrating with EGEE DJRA1.3.
01-Apr-05
Complete
I
I
Metric
Software release.
Risk/Dep
History
5
2.2.5
GS: Evaluation report on PM07 release (2.2.3)
01-Sep-05
Complete
I
I
Metric
Report following up on EGEE release 1 evaluating the software released in PM07
Risk/Dep
History
ChangeForm1
6
2.2.6
LSM: Evaluation report on PM07 release (2.2.4)
01-Sep-05
Complete
I
I
Metric
Report following up on EGEE release 1 evaluating the software released in PM07
Risk/Dep
History
ChangeForm1
7
2.2.7
GS: Software release integrating with EGEE DJRA1.6.
01-Jan-06
Complete
I
I
Metric
Software release.
It integrates with EGEE’s release 2.
Risk/Dep
History
8
2.2.8
LSM: Software release integrating with EGEE DJRA1.6.
01-Jan-06
Complete
I
I
Metric
Software release:
Integrates with EGEE’s release 2.
Risk/Dep
History
9
2.2.9
GS: Evaluation report of release in PM16
01-May-06
Complete
I
I
Metric
Report
Risk/Dep
History
10
2.2.10
LSM: Evaluation report of release in PM16
01-May-06
Complete
I
I
I
Metric
Report
Risk/Dep
History
11
2.2.11
GS: Plan for final software release.
15-Feb-07
Complete
I
I
Metric
Document describing the plan for the final software release in PM32.
Risk/Dep
History
ChangeForm1
12
2.2.12
LSM: Plan for final software release.
15-Feb-07
Complete
I
I
Metric
Document describing the plan for the final software release in PM32.
Risk/Dep
History
ChangeForm1
13
2.2.13
GS/LSM: Release of GS and LSM integrating with EGEE follow-on.
01-May-07
Complete
I
I
Metric
Software release integrated with a follow-on project to EGEE
Risk/Dep
History
14
2.2.14
GS: Final Project Report for Grid Storage.
31-Aug-07
Complete
I
I
I
Metric
Report
Risk/Dep
History
15
2.2.15
LSM: Final Project Report for Local Storage Management.
31-Aug-07
Complete
I
I
Two additional deliverables completed during the GridPP2+ period - see the 08Q1 logbook
Metric
Report
Risk/Dep
History
[1]
Fill this in with code from Risk Register or use comments to note particular risks or dependencies
[2]
Links to ChangeForms if necessary
[3]
Fill this in with code from Risk Register or use comments to note particular risks or dependencies
[4]
Links to ChangeForms if necessary