ID Name GridPP LCG MSN Apps Pro. Grid
    Li Im Risk Li Im Risk Li Im Risk Li Im Risk Li Im Risk
R1 Recruitment/retention difficulties       2 2 4 2 2 4 2 2 4 2 2 4
R2 Sudden loss of key staff       1 3 3 1 3 3 1 3 3 1 4 4
R3 Minimal Contingency 4 2 8                         This is increased to flag loss of WA
R4 GridPP deliverables late             1 3 3 2 3 6 2 2 4
R5 Sub-components not delivered to project     1 2 2 2 3 6 3 3 9 2 3 6 3 x 3 for castor; not yet a total disaster.
R6 Non take-up of project results       2 1 2 1 4 4 2 2 4 1 4 4
R7 Change in project scope       1 1 1 2 2 4            
R8 Bad publicity 1 3 3 1 3 3 1 3 3 2 3 6      
R9 External OS dependence 3 1 3                        
R10 External middleware dependence       4 2 8 1 4 4 3 2 6 2 2 4 This is glite - apps now reduced to 3 x2 Less dependence on gLite - we'veamelioated risk by using alternatives but still concerns with FTS; SRM2.2; 
R11 Lack of monitoring of staff       1 2 2 2 2 4 2 2 4 1 3 3
R12 Withdrawal of an experiment 2 3 6 1 4 4                  
R13 Lack of cooperation between Tier centres       2 2 4             1 3 3
R14 Scalablity problems       1 2 2 2 2 4            
R15 Software maintainability problems       2 2 4 2 3 6 4 3 12 1 4 4 Increased apps  to 4 x 3; this is the lack of funding for applications;  also increased msn too reflect transition risks to 2x3 (eg SGE)
R16 Technology shifts       1 2 2 2 3 6 2 3 6      
R17 Repitition of research 3 2 6                        
R18 Lack of funding to meet LCG PH-1 goals       4 1 4                  
R20 Conflicting software requirements                   3 2 6 2 3 6
R22 Hardware resources inadequate       2 3 6       2 3 6 2 3 6
R25 Hardware procurement problems       2 2 4             2 3 6
R26 LAN Bottlenecks                         1 3 3
R27 Tier-2 organisation fails                         2 2 4
R28 Experiment Requirements not met                         2 3 6
R29 SYSMAN effort inadequate                         2 3 6
R30 Firewalls interfere with Grid                         2 3 6
R31 Inablility to establish trust relationships                              
R32 Security inadequate to operate Grid                         2 3 6
R33 Interoperability                         2 3 6
R35 Failure of international cooperation       2 1 2                  
R36 e-Science and GridPP divergence                         2 3 6
R37 Institutes do not embrace Grid 2 2 4                        
R38 Grid does not work as required 4 2 8 4 2 8                  
R39 Delay of the LHC 2 2 4                        
R40 Lack of future funding  2 3 6       3 3 9 4 3 12       Left as was;
R41 Network backbone failure                         0 4 1
R42 Network backbone bottleneck                         2 2 4
R43 Network backbone upgrade delay                         1 4 4
R44 Inadequate User Support                         2 3 6