PM09: Persistency scheme for level-1 calorimeter trigger data storage.
- 09/04 Collect/update documentation on all output data formats
Identify additional features needed in simulation
- 11/04 Full set of Bytestream converters implemented.
- 12/04 Decision on offline identifiers
PM12: Level-1 validation requirement capture and design documents
(Note: new 1st level deliverable.)
- 02/05 Draft requirements for MC and data validation.
- 04/05 Design, incorporating experience from testbeam analysis.
PM15: Thorough revision of level-1 trigger calorimeter simulation, including
full hardware configuration
- 05/05 Description of all configuration options in final system,
including identification of those to be added to the simulation
- 06/05 Design of additional/modified components
PM24: Update of level-1 simulation to include experience from prototype
tests (beam and laboratory).
PM30: Level-1 offline monitoring tools available.
PM36: Revision of level-1 simulation in light of experience from comissioning
(Note: changed from "data taking" to "comissioning".)