The ATLAS UK Computing Project

WP1 - Low Level Tracking

Contact: Steve Lloyd   Logbook 

SCT Digitization (QMUL)
TaskDescriptionDueCompleted
WP1.1.1 Prototype of interface between the SCT digitization and Conditions DB 01-Dec-05 20-Nov-05
WP1.1.2 Document data elements to be included in the condition database 01-Aug-05 01-Jul-05
WP1.1.3 Fully functional digi-CondDB interface 01-Mar-06 01-Mar-06
WP1.1.4 Fully functional RDO to ByteStream Convertor 01-Dec-05 1-Jan-06
WP1.1.5 Full test of components in Physics Readiness Data Challenge (DC3) 01-May-06 Deleted
WP1.1.6 Evaluate components with full ATLAS Geant4 model using Cosmic Data 01-Mar-07 Deleted
WP1.1.7 Production versions ready for ATLAS Data analysis 01-May-07 Deleted
WP1.1.8 Evaluation and revision based on cosmic and beam-data. 01-Oct-07 Deleted
SCT Monitoring (Cambridge & Liverpool)
TaskDescriptionDueCompleted
WP1.2.1 Requirements capture and design documents 01-Apr-05 01-Mar-06
WP1.2.2 Prototype monitoring framework. 01-Oct-05 01-Oct-05
WP1.2.3 Efficiency testing classes created and included in the Validation Framework prototype and used as part of the prototype evaluation. Simulation of differing deterioration scenarios and evaluation of monitoring software. 01-Jul-06 01-Jul-06
WP1.2.4 Barrel monitoring included in monitoring framework. 01-Oct-06 01-Oct-06
WP1.2.5 Revised classes and integration into DCS of the automated optimization procedure. Tests with cosmic rays when an installed system is available. Incorporation into the online monitoring. 01-Apr-07 01-Oct-07
WP1.2.6 Extensive off-line evaluation of the procedure using real data. 01-Oct-07 01-Oct-07
SCT Alignment (Manchester, Oxford & RAL)
TaskDescriptionDueCompleted
WP1.3.1 Produce field-fitting programming that can cope with all expected features of field, and is robust enough to cope with “unexpected” features. 01-Sep-05 01-Nov-05
WP1.3.2 Deliver first version of geodetic grid software a) to determine 3D node co-ordinates from FSI 1D data, and b) to interpolate 3D node co-ordinates to provide module co-ordinates. 30-Sep-08
WP1.3.3 First version of track-based alignment software for use in DC3. 01-Sep-05 01-Sept-05
WP1.3.4 Perform X-ray survey. (if “go”) 01-Dec-05 Deleted
WP1.3.5 Complete collection and validation of “conventional surveys” of module ‘internal’ assemblies (module metrology). 01-Dec-05 01-Dec-05
WP1.3.6 Complete collection and validation of “conventional surveys” of SCT support structures (optical surveys, barrel and disk). 01-Mar-06 01-Jun-06
WP1.3.7 First version of full alignment software (using tracks and FSI) into ATLAS. 31-Mar-09
WP1.3.8 Produce field map good to ~1 part in 2000 throughout ID volume, and interface this map to tracking software. 01-Dec-06 20-Apr-07
WP1.3.9 Complete general tool to combine all survey information (including X-ray if done) to produce “initial position” file, and demonstrate that it works. 01-May-06 Deleted
WP1.3.10 Production release of alignment procedure combining initial survey with FSI and track data. 31-May-07 29-Nov-07
WP1.3.11 Complete collection and validation of “conventional surveys” of barrel module ‘internal’ assemblies (module metrology).
Deleted
WP1.3.12 Complete alignment studies of Combined Test Beam (CTB), using global-chi2 and ‘robust’ methods. 31-Jul-06 20-Oct-06
WP1.3.13 Demonstrate functionality of global-Chi2 and ‘robust’ alignment methods on the ‘surface cosmics’ in the barrel. 11-Dec-06 01-Jan-07
WP1.3.14 Interface Field Map to tracking software. 01-Mar-07 01-Dec-07
Core Tracking (RAL)
TaskDescriptionDueCompleted
WP1.4.1 Completed familiarization with ATLAS s/w infrastructure in general and with ID/SCT tracking software in particular (as in Release 10). 01-Jan-05 01-Mar-05
WP1.4.2 Completed sufficient testing/QA of Release 10 of ID software to provide input to Release 11 (to be used for Physics Workshop). 01-Jun-05 01-Jul-05
WP1.4.3 Completed improvements, including support of SCT calibration and alignment, and improved structure for High Level Trigger, for Release 12, which is the production release for DC3. 01-Oct-05 Deleted
WP1.4.4 Studies carried out with DC3 software, and tracking validation contributions written for Physics Readiness Report (June 2006). 01-Oct-06 01-Oct-06
WP1.4.5 Program version delivered for main cosmic ray running. 01-Jan-07 Deleted
WP1.4.6 Revised design implemented. 01-May-07 Deleted
WP1.4.7 Feedback provided based on available data 01-Oct-07 Deleted
Track Validation & Monitoring (Ex Manchester now RAL)
TaskDescriptionDueCompleted
WP1.5.1 Monitoring histograms and metrics implement in the RTT/validation framework. 01-Jun-06 01-Jun-06
WP1.5.2 Major release incorporating feed-back from developers and clients. 01-Mar-07 02-Jun-07
WP1.5.3 Incorporation into ATLAS general data-quality monitor. 01-Jun-07 03-Oct-07
WP1.5.4 Evaluation with available data and minor release. 01-Sep-07 01-Sep-07

Documents

WP1 Alignment August 2006
WP1.2 Design Document
Redirection of WP1.5 Effort
SCT Monitoring Work Plan
SCT Conditions Data Inventory
Performance of the ATLAS ID Offline Reconstruction

Meetings

ID Alignment work in UK 